
abernabei
Members-
Posts
40 -
Joined
-
Last visited
Everything posted by abernabei
-
Heh, I wish it were that easy so many conflicting opinions around... manufacturers recommend adding battens in places where a high load is expected. I don't want to risk the floor slightly sagging over time because I add a heavy load in a place that was previously unsupported, hence why we're going with battens. Regarding the OSB, by "glued and screwed" you mean between them? (or where is it screwed to, if it's floating on top?) Regarding VCL, please see the following for an example, they all specify a VCL above insulation, below OSB/plywood/floor https://www.kingspan.com/gb/en/knowledge-articles/a-guide-to-constructing-a-floating-floor/ https://assets.publishing.service.gov.uk/media/62a0683ad3bf7f036fc493ba/solid-floor-insulation-best-practice.pdf https://polyfoamxps.co.uk/floor-insulation/concreate-slab-insulation/ https://www.permagard.co.uk/advice/installing-vcl-vapour-control-layer
-
All the documents I could find recommend installing a DPM below and a VCL above the insulation (especially for vapour closed setups) to prevent moisture from reaching the insulation and getting trapped between insulation and slab. I could be missing or misunderstanding something though
-
so apply butyl tapes all along the battens wherever we intend to screw the boards down? (30cm spacing on long edges, 15cm on short edges, SpruceFloor recommendations) Do you mean the double-sided one, with the idea that it will kind-of seal the hole once the screw is in? For a similar reason, installing the VCL below the plywood means I wouldn't be able to glue the boards down to the battens to increase stability we have done that on first floor (screwed and glued, no VCL) with excellent results, but it seems like that won't be an option, if the VCL has to be below.
-
thanks for sharing that 👍 I'll be honest, I did think about the silicone
-
Hi everyone, we're about to install some insulation on top of a solid concrete floor. Context: Ceiling height is already very low, so we've got very little space to play with. We've decided to go with the following build-up: - existing concrete - DONE: liquid DPM (mapeproof onecoat) - 25x38mm battens, 40cm spacing between centers. This is to increase stability of the insulated floor (alternatives like PIR and wedi boards were discussed at the linked thread) - 25mm Kingspan K103 phenolic board - VCL? - 18mm SpruceFloor plywood - VCL? (alternative position) - underlay - 12mm laminate (most likely QuickStep Impressive Ultra) to gain additional stability There are a few challenges which I would like to get your opinion on: any advice on how to merge the liquid DPM with the existing DPC? The DPC is very short (60s maisonette in an ex-council block) and neither Mapei nor Ardex mention this challenge in their technical documents. Haven't contacted their technical teams about this matter, yet. given we're going with battens, the plan is to screw and glue the 18mm plywood to the battens. Installing the VCL below the plywood would mean screwing through it to fix the plywood in place, which doesn't seem like a great idea. Is that how it's usually done? I read a number of documents on insulated suspended timber floors but they never mention how the floorboards are then fixed to the joists without perforating the VCL underneath. Would it make sense to install the VCL above the plywood? The kitchen is already in place and we will not be able to Installation guides for the VCL recommend lapping 10cm on the walls, which makes sense but... Where is that taped if the wall is already built? On the finished wall? If so, how would you then install the skirting board on top of it, assuming the VCL will already cover 10cm height from the floor? Nailing the skirting board in place, perforating the VCL, doesn't sound like a good idea...but at the same time you cannot glue the skirting board to the VCL, as that's just taped to the wall... The only option I can think of getting a 15cm tall skirting board and then glueing it in place using the top 5cm or less which are above the VCL... How do people usually workaround that limitation? Does anyone have experience with similar projects?
-
Thank you, and did you screw through the VCL when installing the OSB? It seems like a big no-no, but alternatives are either putting the VCL on top of the plywood (though every best practice document says it should be right on top of the insulation) or laying the plywood without screwing it to the battens, which I fear will decrease its stability. We went with the battens approach as that will allow us to use phenolic foam instead of PIR, and even though there will cold bridges due to the battens, the overall gain should be positive, or at least that's the bet. Laying a floating floor directly on top of PIR (140kPa compressive strength) didn't really convince me, after seeing first hand the 120kPa strength phenolic foam K103 behaves under pressure. (we spoke about the other alternative, wedi boards, a few posts up)
-
Thanks @Ferdinand I had a good read at the linked thread good tricks! In our case, the rewiring has already been started and it's going on the concrete ceiling (second ceiling to be built on top of that). Heating pipes will run below the internal walls insulated plasterboard boards, as those are 62.5mm thick We're having an ASHP installed, too, but unfortunately we couldn't go for UFH because of the big downward heat lost that would create (the concrete floor is not currently insulated). Any reason why you used laths throughout the floor, rather than just at the edges to create the service channels? In our plan there would be no laths Which @JohnMo's idea are you referring to, Wedi boards? It's a very valid alternative, it would give us comparable insulation saving perhaps 5mm of floor height (or less, depending on adhesive thickness) but it comes with a few disadvantages which I highlighted in my previous post. Still a very good option though
-
cool, that was all clear, just wanted to confirm The idea would be to prevent any moisture from above from getting trapped between insulation and DPM, as the DPM is on the cold side of the floor. Does that make sense? However, once the VCL is in place the new risk is moisture getting trapped in the DPM-insulation-VCL sandwich (the assumption is DPM and VCL are not fully sealed so moisture can still get in between those layers.
-
The DPM is a liquid one we installed on top of the existing screed as there did not seem to be any pre-existing DPM. That is under the insulation and stops the moisture from below. The VCL would be on top of the insulation and would the moisture from above. Is VCL the wrong term for it? What do you mean?
-
After going back and forth on what to do, I think I have settled on DONE: Epoxy DPM (already installed, Mapeproof OneCoat) 20mm PIR with fire rating E 18mm t&g plywood or 2 x 9mm plywood. The 9mm do not seem to be available with t&g, I guess because they're too thin. VCL? There are lots of people pro and against it, as it often happens it's not really clear what path to pursue underlay 12mm laminate Regarding the VCL, there are 2 schools of thought: "VCL is a must have": these people argue it is required to stop moisture from above condensing under the insulation layer, which makes sense... "don't do it": these people argue the epoxy DPM and VLC on top of the insulation will create a plastic bag around the insulation and if any moisture were to get in between those layers (sealing the liquid DPM at the edges is virtually impossible, and the VCL might not be 100% sealed either) will get stuck there. These arguments make sense too... Regarding the insulation layer: we ultimately decided against Wedi as we couldn't justify the higher price, considering their flammability and tile adhesive installation method (that's the only allowed installation method, as far as I could read on the official manual). With Wedi we wouldn't need the plywood layer but it would lead to higher installation and material costs and higher risk in case of fire. Any opinion on the proposed plan?
-
current options for floating floor are: - 30mm XPS wedi boards, fire rating E + underlay and laminate (no height for adding plywood unless we decrease wedi to 20mm) - 20mm PIR board, fire rating E + 18mm plywood (or 2x9mm plywood) + underlay and laminate any reason to go for one or the other? I'm tempted to go for PIR + plywood as I feel it might feel more solid despite the lower compressivity of the PIR
-
regarding the choice of beads: we've recently been trying to find out whether we should install beads or wool after extracting the current CWI Most of the installers who attended said they used to install beads but do not anymore because it's too difficult to do it properly... I left some details at Hope that helps
-
Regarding cavity wall insulation: as it turns out, what we believe was sagged wool insulation turned out to be just a sloppy job. Ground floor walls are still mostly full and not moist, first floor is mostly empty. They basically did not the first floor at all. The company who attended said maybe it was done as part of a government funded initiative to insulated council blocks and so the installers had way too many jobs to do in a day to care about insulating it properly. A few companies came over to do a survey and provide a quote. Ultimately, I think we'll be going for wool. I hear a lot of good things about bonded beads, but lots of installers complained about the problems in getting the right amount of glue out of the nozzles. They say they easily clog and it's hard, as an installer, to know when they stop working. They said you need to manually check whether the glue is still flowing, and when it's not, you can't be sure how long exactly you're been blowing beads without glue... That in itself seems a deal breaker to me. Considering the property was already (albeit poorly) insulated with wool and it didn't really sag and it doesn't seem moist, I think going for wool might make more sense. The reason behind that is that if anything goes wrong and the installer does not want to accept responsibility (something that seems to be happening more often than not), beads will be a lot more expensive to extract. What do you think? @JohnMoregarding ventilation: I am catching up on the topic. The current plan is use a MEV for utility and toilet room plus a dMEV in the kitchen area (as well as a ceiling hood), which is not conveniently located to be ducted to the MEV. What do you think? Any recommendations for brands/models?
-
Hi everyone, updates: Concrete ground floor insulation: we dug the screed out a bit here and there. As it turns out, the concrete slab on the ground floor, just like on the first floor, is very uneven. The screed is about 2.5cm thick at the sides, and 5.5-6cm in the middle of the room. That means we would have had to have the asbestos bitumen adhesive ground, then dig out the screed and fill in partially again to make it level before adding insulation. All of that for just a bit more than 2cm of extra height compared to not digging it. For that reason, we have decided to leave the current screed as it is. We are covering it with a "dpm sandwich" - Mapei Latexplan Trade Fast (the "Fast" is an important detail as its composition is like their "No Ammonia" latexplan, i.e. t sticks to bitumen, unlike standard compounds like their Ultraplan 3240 or the standard Latexplan Trade). Moreover, this has much compressive strength than Latexplan No Ammonia. This allows us to do the top coat of the dpm sandwich using Ultraplan 3240, which has a lower compressive strength than Trade Fast and is much cheaper than No Ammonia, which is what we would have had to use as top coat had we used No Ammonia in this first layer too. - Mapei Mapeproof One Coat - Mapei Grip T Plus primer - Mapei Ultraplan 3240 I am posting all these details hoping they are useful to someone else in the future, as this was all approved and recommended by Mapei's technical support (indeed, the idea to use Trade Fast to allow using Ultraplan 3240 on the top coat was their recommendation) On top of that, I'd like to add some insulation but without losing floor height. Question: what do you think about using - insulated cement boards, like 20mm XPS with 0.5mm glass-fibre mesh reinforced polymer-modified cement mortar. or - XPS 400-500kPa or - EPS 400kPa and then install the underlay and laminate straight on top of it? Would it work, given the high(er) compressive strength? Or do we really need to lose another 18/22mm for chipboard/plywood? There is no floor height for having that extra layer of chipboard/plywood, so if 400-500kPa boards are not enough by themselves, I think I'll have to let go of insulation
-
yeah taking up the screen would be ideal...I'm a bit concerned about what's going to happen once we do remove that, assuming we're even allowed... so for now I think we're only considering proposals on how to insulate on top of the existing screed. P/A is about 0.4 I am also a bit unsure whether it could make sense to keep the thermal mass of the current screed+slab rather than going through a lot of disruption to add just a bit of insulation on top of it, partial decreasing thermal mass. I am hoping that's not a problem as entrance and patio doors are already at a higher level. The rest of the doors were to be replaced in any case, frames included.
-
The infrared panels were advice from an architectural techonlogist 😅 Thanks for the advice, I suppose by "board" you are referring to the chipboard (which will spread the load). As this will be the main living room, kitchen, dining room area it's the place that will see highest foot traffic, especially during parties etc
-
Thanks for that, Liam. At the moment, we are looking at adding "some" insulation on top of the screed. I did some research, it seems like we could add the following on top of the current screed: - DPM - 25mm XPS board (Polyfoam XPS?). Could we use PIR too? or is the lower compressivity a deal breaker? - 18/22mm P5 chiboard (or 18mm plywood like Wisa SpruceFloor) - 5mm laminate underlay - 12mm laminate The subfloor could also be done using StyroFloor, I suppose? Would that be preferable even to the plywood option, given the chipboard is already glue to the insulation?