  1. Hello, I am converting a property into 10 student accommodation flats. A three-phase supply is required and we received an offer for an MSDB board 180KVA. Today I was told by National Grid, that with an MSDB board we will require 10 separate meters in either the rooms or the communal areas. As this will be student accommodation and all bills included, I'd rather have one meter positioned in the existing meter room. National Grid told me that for this, only with a Cut Out will it be possible to have one meter only. Can someone please help me out with this? - What is the difference between a Cut Out and MSDB? - How does the difference between the two impact the number of meters required?
×
×