bmj1
Members-
Posts
162 -
Joined
-
Last visited
Recent Profile Visitors
The recent visitors block is disabled and is not being shown to other users.
bmj1's Achievements
Regular Member (4/5)
32
Reputation
-
Options for cladding steel beams and column
bmj1 replied to SBMS's topic in General Self Build & DIY Discussion
Could be stunning clad in stone. Won't be cheap. -
Adding MVHR late in the day
bmj1 replied to bmj1's topic in Mechanical Ventilation with Heat Recovery (MVHR)
Yes exactly. Not done the test yet, will be interesting to see. -
Adding MVHR late in the day
bmj1 replied to bmj1's topic in Mechanical Ventilation with Heat Recovery (MVHR)
Very. We dry lined with insulated plasterboard and it's a new build. And yes the doors are undercut. I'm inclined to give it a go unless someone tells me otherwise -
Adding MVHR late in the day
bmj1 replied to bmj1's topic in Mechanical Ventilation with Heat Recovery (MVHR)
We've got an mvhr unit on the ground floor bring fresh air into kitchen and extracting air from toilet/boiler cupboard and under stairs. The rest of the house has trickle vents that we can open and close as needed. My thinking was to install this in the master bedroom area and then close the trickle vents in that area. We've got dmev fans in the other wet rooms running continuously. -
We're looking at adding some MVHR quite late in the day... (ceilings already up, plastered and painted, walls painted/tiled, we've already moved in and are finding the master bedroom quite stuffy). This minimises what we can do in terms of ducting runs (without damages and so costs being prohibitive). Floor plan showing master bedroom/dressing/ensuite here: I was thinking to do the below, i.e: - MVHR unit in the ceiling (above joinery) - duct straight outside for the in/out - extract out above the shower in the en-suite - fresh air into the master dressing room - drainage straight out into the guttering (outside) From those with experience, do we think this will be sufficient to create a flow of fresh air throughout the master bedroom ? Thank you in advance !
-
I also did checked and splayed reveals at the front of our house, gives a nicer visual externally by hiding some of the window frame, and it's a nice detail internally with the angled reveals.
-
Hi all, We've got beam and block ground floor, and a 150mm cavity. I'm just figuring out the best way to close the front door threshold: Questions: 1) Should I put e.g. 100mm of PIR in the gap ? Should it be wrapped in plastic ? And then fill the remaining 50mm void with concrete ? Should I wrap the concrete in plastic ? 2) I've got some spare insulated board on site (link) - which I could then use to bridge the threshold 3) Are there any other considerations in terms of DPC or drainage ? It's going to be a flush threshold to a raised step in front (not yet built) 4) Any principles I need to apply here ? Thank you in advance.
-
We aren't yet in - ask me again in a few weeks
-
Thanks both - all sorted !
-
I've got a suspended ceiling grid, with the plasterboard now up and skimmed. Speaker cut-outs have been made, and ceiling painted, and unfortunately 1 of them clashes with the grid (it's about 20mm out). Option 1 is of course to redo the cut-out, repair the ceiling and repaint. Is there an option 2 where we add a piece of timber adjacent to the piece of metal that is in the way, screw through the metal to the wood, and then cut the piece of metal that is in the way ?
-
Hi all, I have a question, and will be grateful for advice. In A JCT Intermediate Building Contract, where: The contractor has charged for "Temporary Protection" as part of their preliminaries; and Where a named sub-contractor has laid flooring; and The Main Contractor has been paid Overhead & Profit on this item - Who is responsible for organising temporary protection of the floor, and liable for the cost ? E.g: The Main Contractor; or The Client Thank you in advance
-
We've run some lighting cables from internally through the cavity to our bricks on the front of the house. (We've now closed up/plastered/painted). The lighting cables are loose, coming through the brickwork/mortar. I'd like to use these: https://www.downlightsdirect.co.uk/eyelid-led-marker-light.html Our electrician is advising this isn't feasible as there is no ability to make a connection (e.g. with junction boxes). Is there a solution that means we could use these? I love the elegance of these. E.g. some kind of way of doing the connection without use of a big junction box, etc ? Something like this perhaps ? Set out like this: And then combined with heat shrink tubing ? So the end result would be this, which could then fit in the holes in the brickwork ?
-
I need to close a couple of door reveals, with fairly minimal thickness/build-up. Dot + dab insulated plasterboard is going to take 40mm+ of build-up. Could I use tilebacker board/wediboard (these are good for insulation) ? And then plaster skim on top ? How would I fix it to the concrete block ? Thank you in advance.
-
Glazing has been cut too low for the channel. Glazer says they can't redo unless the tile above is removed as not possible to slide it in, and is blaming the builder. Builder says they can't remove the tile above, and is blaming the glazer. I'm stuck in the middle, trying to figure out the best way to fix it, my current thinking is to use some kind of saw to grind back the channel above the glass, and then fill it with marble dust. Thoughts?
-
Yes. It's often referred to as a "slip membrane", can be the thinnest/cheapest plastic that can survive a couple of days of foot traffic as you lay the ufh piping and pour the screed. VCL isn't really the best term for this layer.