Jump to content

Groundwork and Landscaping


jonM

1219 views

We make a start on 15th October with the diggers arriving on 16th October. By the 17th October, state of play is as per the picture below. The gabion wall on the right of the plot was put in by the vendor as part of the infrastructure works. The trench on the left is for a gabion wall that we are putting in on the other boundary. As there is quite a slope from back to front, we are putting another gabion wall across the plot to act as a retaining wall. All OK so far, but there is a surprising amount of muck that came out of the trench for the gabion wall which will need to be taken off-site. On the plus side, the plot had already been stripped of topsoil and as we are using a passivhaus foundation there was not too much extra muck on top of this. 

 

The builder we are using has been involved since the early stages of the project. We didn't go to competitive tender but worked with the Architect to look for someone with experience of the build method we are using who we felt would be able to build to our budget. We are living around 3 hours drive from the site and made a decision out of necessity to continue working in our day jobs throughout the build, however we are purchasing all of the materials ourselves or via our own accounts which we expect will make the build more cost effective. This arrangement works to my strengths as whilst my practical building skills aren't great, I should be OK tracking costs and getting good prices on the materials. 

 

1269638893_IMG-20181017-WA0003(002).thumb.jpg.627d5cc841a8c968875627eaf4f3d004.jpg

 

Original plan was to get the gabion cages in place and fill them as time allowed, but the Passivhaus foundation could not be delivered for the requested date of 24th October, so once the drainage is complete,  filling the gabion cages becomes the main task to keep the team onsite busy. By 26th October, the majority of the drainage and gabion walls are complete

 

13649106_IMG-20181026-WA0001v2.thumb.jpg.229f5cb91c5b3f90731e4fc1089b199e.jpg

 

The following week is spent finishing of the gabion walls, landscaping, groundwork and preparing the grit base for the Passivhaus foundation. There is however a further delay on the Passivhaus foundation, so a decision is made to push on with the garage to keep everyone on site busy. 

 

194419914_IMG-20181031-WA0004(002).thumb.jpg.3b3f3919befb0cce28714b75f7fa9e41.jpg

 

At the end of the week (2nd November), the slab for the garage is laid 

 

IMG-20181102-WA0002.thumb.jpg.bffc88180bf16bc394edb2a6bef7511a.jpg

 

The garage progresses quickly the following week and the Passivhaus foundation arrives on 8th November. There are some small dimensional inaccuracies with the Passivhaus foundation base that need to be corrected, but I am thankful this is spotted before the concrete pour when it is relatively easy to fix. It is however another delay and distraction we could have done without. On the bright side however, there have been no nasty surprises with the groundwork / drainage.

 

IMG-20181110-WA0004.thumb.jpg.4002880513c2ca27975a6d582e8e6001.jpg

 

Work continues on the garage w/c 12th November with prep for the house slab starting at the end of the week. DPM and steelwork for the house slab go in on the 19th and 20th and following a review of the weather forecasts, we go for the 23rd November for the concrete pour. The concrete and concrete pump are ordered again, the rain holds off, temperature is ok and the pour goes to plan. Garage has also now been boarded. 

 

IMG-20181123-WA0001.thumb.jpg.ba1ce3aa70f2256db56eb7b8c2ae2d89.jpg

 

IMG-20181123-WA0007.thumb.jpg.620f311342c8c62da9ef1676085f4d3b.jpg

  • Like 9

0 Comments


Recommended Comments

There are no comments to display.

Create an account or sign in to comment

You need to be a member in order to leave a comment

Create an account

Sign up for a new account in our community. It's easy!

Register a new account

Sign in

Already have an account? Sign in here.

Sign In Now
×
×
  • Create New...