Internal Finish - Upstairs!
Decided to buy the materials I need to finish the direct surround of my house before Diesel shortages and goodness knows what else takes hold!

50+m2 of paving blocks, 3 tons of paving grit and a full load of type 2 MOT to spread around the house next month!! I plan to get bound resin for the driveway, either do it myself or pay someone (£150 per square meter though and 50 m2 so 7.5K and thats with me doing all the edging and subbase prep!!).
Still there's a couple of wheelbarrows in the materials above to do in the meantime and I did the driveway in my old house next door (fully paved) and it's stood up well. Plan on having a step up to the front door but a ramp off to the right as an alternate path.
Have been working upstairs getting things finished. Currently have the stairwell, landing and office room completed and kitted out. Just starting the Master bedroom this week. Then it's off to the outside! I bought a pull out sofa bed, extra computer desk and some IKEA PAX wardrobes for the office room. There wasn't space for 4 Ikea units (500m wide each) so I put in 400mm wide shelving instead - I'll paint at some point. I forgot to level the sides of the double wardrobe before tacking on the back so while the sides are parallel, it's more like a parallelogram and one door is offline. Oh well!! That'll teach me to measure twice!! I'm gluing the bamboo floor upstairs also and Iove the look of it. I can now move into it as a full time office and save the space in my bedroom for the first time ever in nearly 30 years (i.e. no computer in my bedroom anymore!).
the two skylights at the top of the stairwell work well. I forgot to clean the upper window and take off the Velux protective tape before taking down the temporary platform and finish the sides. I won't tell you what I did with a ladder to fix this on all fours and ended up heading back to the Chiropractor the next day!!
The Master bedroom is a bit tighter but I measured it and think I have a bit of room to play around with 2.85m x 3.5m so a double bed and 500mm lockers either side still gives me a meter on one side or the other to add a dresser or something like that, fitted wardrobes over and around the bed and another at the end of the bed. How to fit a locker into an IKEA system? You can build in space with the PLATSA - I did a free design session with an IKEA rep who showed me how. I'll have to move the plug sockets up or they'll get buried but should be ok otherwise. I plan to fit a table above where the soil pipe boxing protrudes.
If you spotted a hole in the wall above the light socket, the door lining screw pierced the electrical wire at that location and all the lights upstairs went out!! Wago repair done. Electrician is out later this week so will have a word!!
Energy usage (last 2 months) so far is 11pm-8am 3562 kWh, 5pm-7pm 71 kWh and daytime 316 kWh. I've been fine tuning my usage with the SigEnergy system and tried using AI for a few weeks but it kept taking from the grid during peak times which was very annoying even when being told not to so I went back to manual and fixed time schedules so that's helped a bit. I hope to get peak to 0 if possible. My overall usage is up but my bill is €60 down from the last one two months ago which is from PV Export, the one thing the AI system was good at! I'll have to have a talk with it at some point! Each export unit equates to 1/2 a peak unit that should have been avoided!! Ah, technology!! I just figured out today how to send excess PV to my car when it's plugged in. I had Givenergy in my old house which went into Administration this week, glad I'm not with them anymore!
I finally got the glazing for the internal window installed. It's double glazed but with a large airgap for sound proofing. I did considered fire rating it but the price would have been crazy. It's comprised of: 6mm Toughened x 20mm black spacer x 6.4 Laminate for safety. The seat worked out well, just need a few cushions!!
My Sigenergy Gateway is being upgraded to 100A from 63A this week. I have an uprated mains supply but it wasn't picked up by the Solar supplier - unlikely I'll draw that much but still nice to have the extra room in Amps if I ever needed it! Unexpected but hope all goes well! Anyway, that's it for now, lots of joint filling on the Fermacell to do this week and sanding....!
Edited by mike2016
duplicate photos
-
1


0 Comments
Recommended Comments
There are no comments to display.
Create an account or sign in to comment
You need to be a member in order to leave a comment
Create an account
Sign up for a new account in our community. It's easy!
Register a new accountSign in
Already have an account? Sign in here.
Sign In Now