Jump to content
  • entries
    24
  • comments
    282
  • views
    8358

Entries in this blog

The Build - Reflections & sign off.

So after a month or so in the house, the time has provided us with an opportunity to reflect on what we have achieved and what if anything, we would change or could have done differently. In truth there is very little if anything that we would change. The rooms flow, the doors open in the right direction and the lights can be switched on and off in the appropriate places. Even the WBS has proven to be a worry that wasn't worth worrying about, as it's position within the hearth is no lo

Redoctober

Redoctober

The Build - Mission accomplished! We're in!!

A busy November saw all the trades coming good, albeit some were cutting it fine for the moving in day – 30th November – However, we have moved in with all the services up and running. Having said that, BT and Openreach have missed the deadlines and as a result we are without any internet, phone line or TV for at least a week! Also the master bedroom built in wardrobes are still be fitted.   The landscapers have finished their work, providing us with a patio area and a driveway area wh

Redoctober

Redoctober

The Build - Now on notice !

Blimey another month on there is a real sense we are getting there. So much so, we have given notice on our rental. We move in on Friday 30th November regardless!   The main emphasis this month has been installing the treatment plant and drainage system. The treatment plant was initially installed, somewhat optimistically, without any anchors only for it to pop back out of the ground within 24hrs, despite being filled with water and the pit filled with pea shingle. Needless to say the

Redoctober

Redoctober

The Build - Nearly done!!

Yes it seems the main phrase for our build currently, is "nearly done" -  As much as September seemed to be a frustratingly slow month progress wise, I am optimistic that we shall see things all come together during October allowing us to move in for November !! Having said that when I look back on the photos that I had taken, quite a bit of progress had indeed been achieved. It is easy to lose sight of such things when you are in the thick of it on a daily basis.   The upstairs i

Redoctober

Redoctober

The Build - Things have got very messy!

Hi - yes things are getting messy but in a positive manner!  I have been very busy these last few weeks, working a full 8 hours or so and a full weekend. The house has now been plastered except for the sitting room. The reason being the chimney still hasn't been completed. Should be done this week I am told! Once it has been done, the plaster boards can be finished off and the room plastered.   Allowing for the rooms which have been plastered to dry thoroughly, I have followed on with

Redoctober

Redoctober

The Build - Getting there

Hi all - a few photos showing the house 95% plaster boarded and some plastering started. Just the cloakroom and plant room off the utility room to complete. Somewhat frustratingly, we will have to wait a full week before the plasterer returns, which holds up the decorating and second fix joinery. The ceilings for the first floor have had two layers of plaster boards fitted, which helps with sound proofing.   Whilst this has been going on, the stone ,an and his labourer have really crac

Redoctober

Redoctober

The Build - plaster boarding and insulation

Yes, now that the first fix has been completed, the plaster boarding has started with the upstairs being done first. The builders will move downstairs an a weeks time or so. Whilst they have been boarding out, I have been installing the insulation for the partition walls, loft space and ceilings downstairs. The insulation being used in the loft space is 140mm - two layers laid at right angles to each other if that makes sense. The insulation used for the partitions is 100mm and the plasterboard

Redoctober

Redoctober

The Build - First Fix

Since the last update, things have pressed on but unlike other activities, the visual impact isn’t as obvious. I have uploaded some photos but sadly they are not very exciting as you have to look hard to see the electrics - Anyway, it's a record. The upstairs has had the same treatment as the ground floor; in as much as the walls have had additional insulation fitted, wrapped in vapour barrier and had service battens fixed.  The last two weeks of July has seen the plumber and electrici

Redoctober

Redoctober

The Build - Stone work commences

A few photos of the stone work that has now started on site, whilst others continue to prepare the upstairs for the first fix. I have also included an image of the "biscuit screed" laid upstairs over the UFH pipes. Close observers and those who have read previous entries, will notice that the windows have been corrected with fire battens fixed. Anyway, the stone is called a local blend and is made up of Perthshire stone, Cumbria stone and Borders Buff. The Quoins have a hint of lilac t

Redoctober

Redoctober

The Build - Insulation ahead of 1st Fix - UPDATE

A few more images showing the completed UFH network for upstairs, the servicing battens downstairs and also some additional "supports" to accommodate the fitted kitchen units. I have really been impressed with the UFH fitter - he has even supplied photos of vulnerable positions so there should be no excuse for puncturing a pipe after the screed and boarding has gone down. You will see the areas left "unpiped" in the en-suite and bathroom areas. The manifold is stored in the landing cupboard

Redoctober

Redoctober

The Build - Insulation ahead of 1st Fix

A quick pictorial update. The ground floor screed has set allowing those involved to install the additional 50mm rigid insulation to the inside of the external walls of the TF which had 120mm factory fitted insulation pre fitted. They then set about putting up the Vapour/Air Tightness Barrier — Protect VC reflective foil. The next stage will be the 50mm service batons and this will allow the electrician to start the first fix. Whilst this has been going on, the UFH pipes for upstairs are be

Redoctober

Redoctober

The Build - moving forward.

What a difference a week makes in the world of self build – Half the roof has been slated, the additional insulation has arrived on site and the liquid screed has been poured. The guys who did the pour travelled from Perth, some 95 miles away – very few firms seem to do this work north of the Border it seems. The ground floor was prepared by the guy doing the UFH and our builder. The company doing the screed dispatched a surveyor the day before in order to measure the various heights

Redoctober

Redoctober

The Build - watch out for the pot holes!

I suppose after the impact of seeing the TF go up within a few weeks, progress on the eye thereafter, was always going to be less so. If that was the only reason, then it would be an element of self building one would have to adjust to. But unfortunately the lack of progress on our build over the last couple of weeks was not just simply down to a trick of the eye! Frustrating yes and in isolation a mere blip, but other things during this period compounded that frustration into real anxiety

Redoctober

Redoctober

The Build - Timber frame erection

It has been 3 weeks now since the last post and the TF arrived as planned. Sadly the tele handler didn’t!! It was two hours late and thankfully, didn’t impact on the delivery of the TF, although the driver was less than pleased being held up for so long. During the second week of erection, we saw the arrival of the large crane which really did pay for itself as it made light work of the roof timbers. A long day for all, but worthwhile. The final week saw the sarking and dormers being

Redoctober

Redoctober

The Build - Scaffolding ahead of TF arriving

By way of a quick update as the TF arrives on the 29th May -  The Car port now has a slate roof on it - the sides and enclosed shed will be finished once the scaffolding comes down, hopefully the larch cladding will be complete within the next 10 days or so. The scaffolders have erected the main structure in readiness for the TF. You will see one section has been left "open" to allow the panels to be fed inside. This will be closed off upon completion. I'm told the TF will be ready for the windo

Redoctober

Redoctober

The Build - Ground works - Final part

The ground works have moved on considerably, no doubt assisted by the fine weather we have experienced since  mid April. The dwarf wall and base for the car port was always the priority as the frame itself arrives to site on Monday 14th May. The main house sub structure is almost complete – the ducting for the electricity cable and water pipes are in as are the drainage outlets. Over the next week or so the sub base will be completed. The TF is due to arrive Tuesday 29th May. You will see I

Redoctober

Redoctober

The Build - The groundworks - Part 3

A few days for the foundations to settle and then the deliveries arrive and the builders set to work again............ The images will show the footprint of the house and utility room together with the walling and dwarf wall on which will sit the oak framed car port.

Redoctober

Redoctober

The Build - Part 1 - The groundworks

Yes, after years of dreaming, thinking,  researching and waiting, work  finally started on our first self build project. After a couple of false starts due to the builder having to finish a job that over ran and the arrival of the better weather, we eventually broke ground on Wednesday 18th April, two days later than anticipated. Annoying yes, but then what can you do? It’s only two days and it’s important to maintain a relationship with your builder. Nonetheless, we are now ready to d

Redoctober

Redoctober

Getting ready for the earth to move!

This is a short update and precursor to the updates that will soon follow once the ground works begin in April. Having now finally sold our house in Milton Keynes, we have made the move north to the Scottish Borders. We are renting a small flat, few miles from our building plot. At £320 per month, I was never going to win the caravan argument! We lost 7 weeks due to the initial sale /purchase of our house collapsing at the last minute. Fortunately it was sold very soon after being put back

Redoctober

Redoctober

Part 3 - A little less conversation, a bit more action!

There really is a sense that we are approaching the business end of our self build project – the thinking, reading and talking has now evolved into making firm commitments and paying deposits to secure various orders. Ahead of our permanent move  to the Borders in February 2018, [Rented accommodation] we travelled to the area in late October with the express determination to finalise matters with a local builder and to confirm the stone we are going to use, the specification for the oak car

Redoctober

Redoctober

Part 2 - Getting ready to move on...........

So, its been nearly a year since my last post and this is what we have achieved thus far. We attended the NEC show in Feb to confirm in our own mind the products / suppliers we hope to use – namely roof tiles, flooring, rainwater goods & windows and doors. Despite our best efforts to remain focused we had our heads turned by a range of wooden windows – Accoya wood – we made some enquiries and after a few weeks we received their costings - £37k for 10 windows, two French doors and 2 exte

Redoctober

Redoctober

Base Camp - finally

Our Journey North of the Border - Around August 2015, I started a blog intending to detail our experiences, as we set about securing a plot of land and planning permission ahead of our self build development. By way of a reminder and introduction, this was the first and only instalment since. Well this is it, we have finally reached a tipping point. Our retirement plans, which were no more than mere dreams and aspirations some 7 -8 years ago, have now become more focussed followin

Redoctober

Redoctober

×
×
  • Create New...