My MVHR parts have arrived šŸ˜€

Ā I have plvcu ceiling/wall plenums and wondering the best way to mount within the ceiling. The mounting tabs are useful but not sure whether to go direct to the underside of the 22mm egger floor above or whether I need to fit a piece of timber for each one and screw into that. Any advice and photos would be really appreciated. Thanks

Posted
1 hour ago, junglejim said:

My MVHR parts have arrived šŸ˜€

Ā I have plvcu ceiling/wall plenums and wondering the best way to mount within the ceiling. The mounting tabs are useful but not sure whether to go direct to the underside of the 22mm egger floor above or whether I need to fit a piece of timber for each one and screw into that. Any advice and photos would be really appreciated. Thanks

I always put a piece of 18mm OSB between each posi, screwed to the underside of the upper chord, and that gives a flat surface to mount to.Ā 
Ā 

The tabs are a bit soft, so use penny washers with the screws.Ā 
Ā 

Note: I always install 75mm acoustic insulation in before ANY 1st fix or M&E begins, as it’s so much easier to have that lost between the upper chords, and near zero effort to fit it as zero obstacles. Then you have the whole void for services etc.

Ā 

Ergo, the 18mm OSB is requisite to fly over the 75mm acoustic batts.

Ā 

I don’t fix anything (routinely) to the Egger / P5 as it’s ā€œnot the done thingā€.Ā 

Ā 

Couple of battens for this one as other services too close to use a bridge of OSB, but gives you an idea.Ā 

9B90AEA0-1609-4DD6-A9FA-EDCE4880D5C3.thumb.jpeg.9a8fbc681fd6fcdab80b6b8b520028cd.jpeg15687EDD-5BBF-49D4-9901-58ED78732832.thumb.jpeg.3d58d6f4d4405561e328c29180d0fdf9.jpeg

  • Like 1
Posted
23 minutes ago, Nickfromwales said:

I always put a piece of 18mm OSB between each posi, screwed to the underside of the upper chord, and that gives a flat surface to mount to.Ā 
Ā 

The tabs are a bit soft, so use penny washers with the screws.Ā 
Ā 

Note: I always install 75mm acoustic insulation in before ANY 1st fix or M&E begins, as it’s so much easier to have that lost between the upper chords, and near zero effort to fit it as zero obstacles. Then you have the whole void for services etc.

Ā 

Ergo, the 18mm OSB is requisite to fly over the 75mm acoustic batts.

Ā 

I don’t fix anything (routinely) to the Egger / P5 as it’s ā€œnot the done thingā€.Ā 

Thanks that’s useful. Still trying work out the best build up for my ceiling. The posi joists upper cord is about 45mm and there are regular noggins with the same gap above so thinking maybe 50mm Rockwool rwa45 then MVHR ducts then another layer of acoustic insulation. I feel like the ceiling should have as much insulation as I can get in but realise I also don’t want to be insulating the wiring . I’m probably way off here so really interested in what others do… another steep learning curve!Ā 

Ā 

Ā 

IMG_3370.jpeg

Create an account or sign in to comment

You need to be a member in order to leave a comment

Create an account

Sign up for a new account in our community. It's easy!

Register a new account

Sign in

Already have an account? Sign in here.

Sign In Now
×
×
  • Create New...