PSC88 Posted 11 hours ago Posted 11 hours ago Hi just hoping the forum can help shed some light on the building regs after full approval. i have full planning approved and then my architect submitted building regs. I was initially given a refusal on one of the discharge conditions on materials. i resubmitted materials and council provided an approval on the the materials discharging the conditions. Am I now good to go? Or should the council be providing some form of building control approval on the construction drawings? im not using my council for building regs im using a private company. im demolitions a bungalow so have submitted a demotion notice Many thanks