Just thought I'd provide some positive feedback about Stroma.

 

They came to site this week after a brief call to discuss completion. The BCO arrived and we had a quick walk around, he knowing we had been doing most of the work ourselves. Apart from being complimentary, he explained he would NOT do a completion visit report as that would only give us 8 weeks to finish and he could tell that wasn't going to be possible. So we have a progress report only, with 8 items.

 

Maybe 2026 will bring completion 😀. On second thoughts ....