Hi all,

 

I have just had a shell only extension done. The subfloor is down upstairs but joists can be accessed from underneath. The ground floor is a suspended timber floor which is just joists at the moment with a large void/crawl space underneath. 

 

I will be putting up the stud walls on the first floor shortly and I know that now is the time to get the plumber and electrician in. Is there any particular order you guys recommend? I know plastering is done at the end after 1st fix but surely the wall that the boiler is mounted on will need to be plastered first before boiler installed and pipework run.

 

 

Link to comment
Share on other sites

You can get the plumber and plaster in any order 

But most will get the plumber first 

Easier to run wires around pipes than the other way round 

Your plumber will put the pipe work in for the boiler and put the boiler in with the Rads bath etc on a second fix after plastering and paint 

Link to comment
Share on other sites

Create an account or sign in to comment

You need to be a member in order to leave a comment

Create an account

Sign up for a new account in our community. It's easy!

Register a new account

Sign in

Already have an account? Sign in here.

Sign In Now
×
×
  • Create New...