Post and beam Posted October 27 Share Posted October 27 Kingspan ultima SIPs construction. Our frame erectors are almost finished after only 3 weeks. The membranes, numerous, are being unfolded and stapled. The basic airtightness will come from the SIPs panel but i wonder if what you can see in the picture also needs to be taped along the edges. Link to comment Share on other sites More sharing options...
IGP Posted October 30 Share Posted October 30 Need, no. But you could for that extra bit of performance. Link to comment Share on other sites More sharing options...