Dear All,

 

My scheme consists of cladding (rendering) the front elevation of the property and a side extension under PD.
 
The LPA have subsequently enacted a Conservation Area, effectively removing the right to execute the works under PD.
 
However, I commenced the rendering works prior to the enactment of the Conservation Area so I am lawfully able to complete these.
 
Critically I see the scheme as a whole (i.e. rendering and side extension together) therefore as such I believe I am permitted to also lawfully construct the side extension in order to complete the scheme. 
 
I would appreciate any view you may have on my assertions.
Link to comment
Share on other sites

For safety you could apply for a certificate of lawfulness on the grounds you started work before it became a conservation area. Include copies of any drawings and dated invoices you have.

Edited by Temp
  • Like 2
Link to comment
Share on other sites

Create an account or sign in to comment

You need to be a member in order to leave a comment

Create an account

Sign up for a new account in our community. It's easy!

Register a new account

Sign in

Already have an account? Sign in here.

Sign In Now
×
×
  • Create New...