Peter_J5 Posted April 28, 2021 Share Posted April 28, 2021 I Posted this earlier. But it would have maybe better to post in this section. Link to comment Share on other sites More sharing options...
markc Posted April 28, 2021 Share Posted April 28, 2021 Its just so difficult to estimate, even more so at the moment. Factors to consider are access for plant/digger etc, removal/disposal of excavated material, cost of materials, shortage of labour etc etc. Even the big contractors are offering sil;ly money to trades people to attract them to site (thats if they can get enough materials). Big shortages of materials across Europe due to demand so costing is a nightmare. Link to comment Share on other sites More sharing options...
Peter_J5 Posted April 28, 2021 Author Share Posted April 28, 2021 I noticed timber prices are increasing. I made a back of the envelope calculation for c24 timber. It's gone up in-between things about and extension and having the plans finished. Link to comment Share on other sites More sharing options...
Moonshine Posted April 28, 2021 Share Posted April 28, 2021 3 minutes ago, Peter_J5 said: I noticed timber prices are increasing. Steel as well. Link to comment Share on other sites More sharing options...
Recommended Posts
Create an account or sign in to comment
You need to be a member in order to leave a comment
Create an account
Sign up for a new account in our community. It's easy!
Register a new accountSign in
Already have an account? Sign in here.
Sign In Now