October 14, 201610 yr Does the CDM F10 'Notification of construction project' apply to a self builder who is project managing?
October 14, 201610 yr HSE advice via CITB here : https://www.citb.co.uk/documents/cdm regs/cdm 2015 - qa 3 self build projects.pdf Construction Plan is detailed here - doesn't need to be war and peace http://www.hse.gov.uk/pubns/cis80.pdf
October 15, 201610 yr Author Thanks just read CDM 2015 part 4. I can foreseen someone cutting themselves on site, therefore the implication is I need to provide basic first aid kit on site somewhere. Correct? Is this happening in practice? Fire fighting: am I expected to provide a fire extinguisher?
October 16, 201610 yr The standards are listed out on the HSE website. http://www.hse.gov.uk/construction/safetytopics/siteorg.htm Extinguishers are an odd thing as due to the many types available for each material fire you could nearly end up needing one of each ..! The last big site we did had foam extinguishers as the view from CDM was the biggest risk was from hot work causing a fire with timber or similar. Don't forget that if it's in an unheated space in winter that you will need suitable frost protection for any water based extinguishers.
Create an account or sign in to comment