Just a quick heads up for anyone who may need to change the location/route/type of electricity supply over the next couple of months and how long this may take.
My supply currently comes in via an overhead line attached to a pole very close to the new build. And it's very ugly. Therefore, I plan to get a new pole on the boundary of our property then run the line in via a trench that the groundworker will dig.
I already have my quote but thought I better call Dave, my friendly local DNO installer, to see how busy they are. Good job I rang! The earliest he has available from today for this type of job is 17th October and he's getting booked up quickly.
This date works out okay for me as there's lots of groundworks to be done between now and then, but it could catch you out if you are in a hurry, so always best to check as early as is feasible.