At long last we are starting. 3 months late but at least the weather has improved.
Spent all week excavating the slab base.
4 days of digger hire, 260 tonnes of muck removed, 80 tonnes of type 1 brought in.
Mbc are laying the type1 as the slab has a ring beam around the outside so it needs to be built up first before the main base is laid