Hello all!
I'm looking to re-felt an existing flat roof on a town house in Crawley. It hasn't been touched for a good 30 years, although it has been repaired so is leak-free.
I had a telephone chat with a duty surveyor for Sussex Building Control who seemed to suggest that a building control application isn't needed
This is because the deck and below isn't being replaced, only the top felt, with additional warm roof being added on top of the existing structure.
Would be good to know of anyone else's experiences! Thanks.
Below is a rough outline of what we are planning.
* Remove all existing roof covering to bare timber deck
* Apply SA bitumen primer to whole of roof
* Apply first layer of torch safe vapour control layer
* Fix 50 mm timber kerb around whole of outside edge
* Lay 50mm flat roof insulation boards
* Create new timber outlets to downpipes
* Apply torch on sanded underlay
* Fix 100mm GRP drip trims to outside edge
* Apply Technotorch mineral capsheet to finish