Jump to content

Drunkenmunkey

Members
  • Posts

    8
  • Joined

  • Last visited

Recent Profile Visitors

The recent visitors block is disabled and is not being shown to other users.

Drunkenmunkey's Achievements

New Member

New Member (2/5)

4

Reputation

  1. NEC Contract? Option B? It's remeasurable. I would push for a lump sum/ activity schedule (Option A). Risks I see are: Site clearance is an allowance. If more than one day, this will increase per day by the sum. Grab load allowance - As above for the allowance, how much is a grab load? I would want a lump sum for this and the site clearance. How much vege' are they clearing? Reduced level dig - Is the site already level? i.e. a scrape with a bucket. Or is the site signifcantly undulating? If it's flat then I would ditch this and go with a single JCB + driver for a 2 days at around £1500 allowance. Also, is the 200m3 correct? = 500m2 clearance area for 400mm. Spoil removal is 80m3 - What they doing with the other 120m3? Is that the trim formation level? i.e. landscaping. Drainage and water supply look OK for risk. Prices seem reasonable but I'm not Cambridge based so won't claim to know. Off-site drainage - This can vary a lot and depends on your site plan. Does it include traffic management etc? Off-site services - That doesn't look unreasonable to me as a sum. And you look fairly protected from risk, it'll only change if the meterage goes up. It's always worth getting them out to site first so they can measure up themselves and take decisions. That way, if they argue a change then you have the security that they had a site visit to include these things and price accordingly, which places it as ther cost.
  2. Interesting, can you expand on why Edinburgh may not be like other build sites? Ah, the total sum is the land + build costs.
  3. Hi All, Great site, I'm planning a self build on a beautiful site (not yet bought) but I'm totally green. Any tips or advice is most welcome! I would need to borrow about 1/2 the total sum, is this a reasonable starting point? The rough plan is to take a ~50% loan for the land, then further staged loans of around 60% each time. Does that sound sensible? I look forward to learning from the forum and sharing my experiences! Cheers
×
×
  • Create New...