Jump to content

john0wingnut

Members
  • Posts

    128
  • Joined

  • Last visited

Recent Profile Visitors

The recent visitors block is disabled and is not being shown to other users.

john0wingnut's Achievements

Regular Member

Regular Member (4/5)

12

Reputation

  1. Evening all, Hopefully I have put this is the correct part of the forum. We are in the process of renovating our bungalow, and we are currently focusing on the front of the house. Plan was to add wood fibre EWI to the gable and porch, then clad the gable and render the porch, to improve insulation and appearance. Originally a 1970s bungalow, and previous owners carried out various extensions and alterations to it. Below is an original picture and a current picture of the front of the house: The gable wall was fully cladded with exception of the corner returns of masonry from the side walls. Prior owners opened up the wall and put a porch on, and essentially stitched the new outer leaf into the original, up to where the window lintels are. Above this it remains original block, which is inset about 30-40mm depending on where you measure across the front, to allow for the cladding and battens. I pulled a window cavity closer out and can confirm full fill cavity batts have been used up to the window lintels Now, inside the porch, we have an inner door to the house. Above this there are 2 concrete lintels, with about 20-25mm gap between them. Through this gap, I can see all the way up the gable cavity and there is a constant draft coming through............. explains why the porch was always cold. I can currently think of 2 options to resolve this, which I have put below, but would appreciate what others think of those options and/or if there are any other ways others would approach it: 1) Should I remove the plastic cladding, battens and block outer leaf above the lintels, and then rebuild with blocks aligned to the outer leaf and full fill with cavity batts, up the gable, and use something like Siga Fentrim tape to seal off that gap in the concrete lintels, then install my EWI / new cladding to the whole gable end. 2) Should I remove the plastic cladding and leave the upper block work and battens as is (eg inset), seal off the lintel gap and then get upper gable cavity filled with EPS beads, and then install the EWI and new cladding over the top of the existing inset blocks / battens? Many thanks John
  2. I might just buy a load of 15mm wide 1-7mm expanding foam tape and use as required then.
  3. Internally I will be using SIGA Majrex 200, and the advice with that is to is use Fentrim tape or Primur tape to bond the membrane to the brick, and then use Sicrall tape on all the other corners / joins between membrane etc. This membrane will also be taped to the DPM. Externally I will be using SIGA Majvest 700 Black UV membrane. This will be taped to the roof deck before timber hard edge fitted, and I will also tape the deck joints with wigluv or fentrim tape Re DPC junction, I had planned to leave excess DPC hanging out, then bring it up over the Steico Protect boards and tape external membrane to it. Not sure if that will work mind. The DPC is at the minimum 150mm above FGL, and cladding also finishes at this level on the detail, so if I taped down over that joint onto the bricks, I would end up seeing the tape as it would be lower than the cladding. Re Masonry junctions: Roof deck - was going to use expanding foam tape in this gap. Walls - external membrane brought behind and around first batten, SIGA primur sealant put in gap, then pushed against masonry, and screwed in. Expanding foam tape could also be used here. What I wasnt sure about is whether one needs to detail each element as you go, or just belt and braces internally / externally with membranes and all is well, so to speak
  4. Hi all My timber frame extension will be coming off of a masonry gable end and sitting over a brick / block foundation to DPC level. Should one be using flexifoam / expanding foam tape behind the ledger board / under the soleplate / between first stud and masonry etc to ensure airtightness? I've also seen that one could use EPDM / Neoprene foam which can come in varying widths and thicknesses. Might sound daft to ask, but if using a foam tape, should one apply 2 rows to the timber, so the timber is pulled in flat to the masonry / block? Eg if you put a foam tape only on the outside edge, it may angle the timber slightly when tightened in/down. Or am I massively over thinking this?
  5. I decided they are going on the outer skin, so reveal matches the windows. I managed to remove the inner skin of blocks across the bifold width today and levelled off the cavity infill to match that of the floor slab. I then cut down some new blocks to the level of the concrete slab / infill and have cemented them in. Tomorrow I will lay DPM, fit some perimeter insulation and take 100mm PIR across to the outer skin, slip sheet over top then screed it.
  6. So get some 100mm marmox blocks and put them in the cavity area, and backfill the remainder with concrete, and thus sit the bifold over the cavity area?
  7. Hi all Wanted to gauge the best approach as to where to site a bifold or slider within the depth of the wall, when one is contending with a 100mm cavity. The wall detail is below. This TF is being put onto existing foundations from our conservatory, and thus I am building it over the brick / block and 100mm cavity already there. From foundations (which have been checked by SE) there is 2 courses of dense concrete block and 6 courses of facing bricks, then DPC. 3 courses are above the ground. Interestingly the concrete infill has been done up to 4 courses of bricks - see pic below which shows the current state of it (current conservatory upvc / glazing not removed yet) ........... and yep, going to need to fix the DPC / DPM that the previous lot have hacked out!! I am aware of armatherm, compacfoam and phonotherm as solutions for supporting a bifold over a cavity, however, given the state of the current concrete infill, I would need chip some out and then use some sort of liquid self level to level this off to use compacfoam / armatherm, and phonotherm would raise the door 25mm which affects threshold height. If I stick them on the outer leaf, there is the minor issue of floor tiling over the block / cavity area. This was done previously over the cavity with a cavity closer by prior owners and all the tiles had cracked. If I stick them on the inner block, I need and huge sill and will have huge reveals. Thoughts welcome.
  8. Hey Ive now gone down the route of wood fibre insulation and sheathing boards as it’s all breathable. I used that ubakus tool mentioned above to get my u values sorted etc and it’s also useful to demonstrate phase shifting of heat through the walls and humidity control etc. John
  9. Hi all. It was actually the BCO who raised the issue with the overhang and asked me to discuss with the SE. I was also directed towards info from Trada / NHBC / LABC which advises of 20mm max overhang. The dwarf walls are 9 courses high, but do have a banked concrete infill which is just under the height of 1 internal block. SE came back with a new plan of using an IG9 lintel, but that just adds more complexity, so decided to go with a timber wide enough to span the cavity. I came across Steico joists in walls, which looked like a good option, which I am now exploring. Not exactly building merchant purchase, but there is a firm not too far from me that supplies them. Ive sent my frame plans to We Build Eco, who can then work those into a timber frame kit, which they cut in their factory then ship it up for building onsite. Also includes all sheathing, insulation, membranes, tapes and fixings etc. Will see what they come back to me with. I may well do it myself, or get a local chippy to build the frame, then I take it from there and finish it off.
  10. They were quoting me for it yes. Something like £250, so in the grand scheme of things for my rear extension / porch its a small cost for the extra belt and braces, so I may still do it. Just in contact with We Build Eco now to see whether they will quote me for a shell kit, which I can then build myself.
  11. Well, I spoke too soon. Transpires that the original house, 1970s build, has an extra brick course on the left side vs the right. Im not even sure how that happens, given bricks are done in lines. So I have 2560mm from DPC to undercloak board on the left, and 2440mm on the right, which makes the above plan impossible now, as the fascia boards will never align. So I think my only option now is to lower the wall plate to 2350mm, then mount rafters on hangers on inside to allow enough space to fit a new tiled roof under the current one.
  12. Exactly my plan When the conservatory was built they have put some wool batts in the cavity, however, its not been done very well. I pulled out one section and can see to the bottom, where the banked concrete infill is. My plan was to remove the lot, then fill the entire thing with polybeads. Majpell could be removed as you say. It wasnt in my plan originally, as, like you say, I was going to tape the OSB joints, but when I spoke with the insultation supplier, they advised adding it. John
  13. Pretty much what I’m now going to do. 240mm I joist frame. Cladding Battens Tyvek UV Facade 40mm Steico Duodry 240mm I joist with full fill steicoflex 36 18mm OSB Majpel 5 membrane 40mm service void with steicoflex 36 PB and skim
  14. The dwarf walls are already built and in place, as they were part of the conservatory, so there wont be a 140mm block, as its 100mm. The external face of the new TF will be vertical cladding, so masonry outer is staying as it is, with new TF dropped on top.
  15. Morning Looking for some advice from the forum. I am doing a conversion of my conservatory into a proper room, so a rear extension. Existing foundation and dwarf walls are being retained, and the plan is for a timber frame to be put on top. SE have put forward their plans which shows the 150mm TF sitting on the 100mm block and 50mm overhanging the cavity unsupported, see below. I queried this BCO when drawings were being reviewed by them, and they responded, advising they would expect the soleplate to be over both internal and external leaf's. I subsequently raised this with the SE, who asks to speak with BCO directly, only to be told BCO don't get involved with design aspects of the building, so wouldn't comment. I feel like piggy in the middle now, and not quite sure what to do, and whether what the SE has put forward is ok? As an aside, I had planned to put a row of Marmox blocks on top of the exiting wall, however, their guidance states max 20mm overhang and TF central over the block. Ive also read online that if one has the rafters notched to the outside of the wall plate, this could cause an eccentric load on wall, given the 33% unsupported. I also had a read through the LABC manual which sites 20mm max for 140mm studs............. Keen to hear the views / thoughts / advice from others on hear.
×
×
  • Create New...