This is the quote for what they called the NON-CONTESTABLE work
HV Overhead Main
Installation of an HV pole, associated steelwork and HV stays
Removal of an HV pole, associated steelwork and HV stays
Dismantle span of HV overhead line
Raise and connect HV pole termination
Install & remove a temporary HV safety earth
Install 11kV 185mm aluminium Triplex mains cable down pole
Install pole mounted HV fusegear
£21,869.20
HV Underground Mains
Excavate & Reinstate HV joint hole in unmade ground
Excavate & Reinstate HV trench in unmade ground
Install 11kV 185mm aluminium Triplex mains cable in trench
Install 11kV cable to duct or cable tray
Supply only of 11kV 185mm aluminium Triplex mains cable
11kV 185mm to 185mm Triplex branch joint
11kV 185mm Triplex to 95-185mm PILC straight joint
£14,648.22
Miscellaneous
High Voltage shutdown
Notification of High Voltage shutdown to affected parties £5,389.61
Legal fees for the arrangement of an Easement in relation to UKPN assets
TOTAL £41,907.03