Jump to content
  • entries
    33
  • comments
    180
  • views
    15881

About this blog

The slow crawl towards building a new home in Dublin....

Entries in this blog

1st Foundation Completed

Concrete was poured via a pump on Monday. Finally have a Concrete sub foundation!  Took delivery of the Kore insulation for the actual foundation. Lots of angles sheets, L shape and other ones. I've 88 silver EPS boards too in packs of 8. They needed 2 men to move, the others could be handled one by one. The delivery driver helped offload as getting a forklift and driver for 4 Pallets (@150kg each) was going to be expensive and on too much short notice to arrange insurance for me to drive o

mike2016

mike2016 in foundations

×
×
  • Create New...