Mick78 Posted October 13 Share Posted October 13 Hi all, I am doing a detached garage conversion and have a question on dpc and dpm. Walls are single leaf cavity block and existing dpc is 45 mm up from concrete slab. I plan to DPM the slab and run it 150mm up the walls, then 75mm insulation, then floating 22m chipboard t&g. As the level of the new floor will be over the level of the dpc in the wall, is that a problem I.e. the dpc will be buried half way up the floor insulation. Thanks Link to comment Share on other sites More sharing options...