Is there anyone familiar with Irish Building Regs? If so, would I be correct in saying that if you follow the TGD’s, by default you adhere to the building regs?

 

Whos job is it to check that the work is being done as per TGD’s? Architect? Or the tradespeople?

 

If you were unsure of the TGDs are, is online the only place to find them? 
 

Thanks

Link to comment
Share on other sites

Hi, 

 

I have a little bit of experience with this - based in the North but have dabbled in the South.

 

There is a BCAR process in the south - which can be complicated enough. Your designer/architect has a responsibility to design to regs and will have forms to fill out along with there submission to say they have done.  Managed on the BCMS.

 

The builder has a responsibility to build in compliance with the regs and will also submit forms confirming so.

 

Designer/Builder and owner all have responsibilities. 

 

Many architects/designers act as assigned certifiers and they also have a responsibility to ensure quality, all parties are performing and compliance. 

 

Before you start on site you will need a commencement notice.  You may need your DAC, FSC, technical Drawings submitted to the local council before you get this, and an assigned certifier appointed.

  • Thanks 1
Link to comment
Share on other sites

  • 2 weeks later...
On 23/08/2024 at 11:15, Hughgo12 said:

Hi, 

 

I have a little bit of experience with this - based in the North but have dabbled in the South.

 

There is a BCAR process in the south - which can be complicated enough. Your designer/architect has a responsibility to design to regs and will have forms to fill out along with there submission to say they have done.  Managed on the BCMS.

 

The builder has a responsibility to build in compliance with the regs and will also submit forms confirming so.

 

Designer/Builder and owner all have responsibilities. 

 

Many architects/designers act as assigned certifiers and they also have a responsibility to ensure quality, all parties are performing and compliance. 

 

Before you start on site you will need a commencement notice.  You may need your DAC, FSC, technical Drawings submitted to the local council before you get this, and an assigned certifier appointed.


 

Thanks Hugo. What are DAC and FSC drawings?

 

Would I be correct in saying all new work carried out needs to adhere to the building regs / TGD’s? 

 

If someone was getting a loft conversion or an extension added on to an existing building, does the builder stick to the TGDs? 
 

If it were my house, how would I check what they’re doing meets the building regs criteria? 

Link to comment
Share on other sites

Create an account or sign in to comment

You need to be a member in order to leave a comment

Create an account

Sign up for a new account in our community. It's easy!

Register a new account

Sign in

Already have an account? Sign in here.

Sign In Now
×
×
  • Create New...