Don33e Posted August 15 Share Posted August 15 Hi All, I have started our porch extension in preparation to under and gauge the amount of effort prior starting our rear extension. The current driveway is a stamped concrete slab, which used to but up against the front door. When removing the section of drive to dig the trench, I have found that there was never any block work below the front door threshold! so rain water over the years has undermined the current porch slab! I will dig out the old slab, so my question is how best to seal the new DPM to the existing DPC ? I intend to: 150mm harcore, 25mm sand, DPM, 150mm insulation, DPM, 100mm concrete. Cheers Don Link to comment Share on other sites More sharing options...