Hi everyone,
I was after some advice if possible please. We have a planning application in to build a two storey rear extension on our property. We were due decision on 03/02. All seemed well, neighbours had both said they were happy with the proposal however the ecologist has asked for a preliminary bat survey to be carried out. They came today and found droppings in the loft which means we need further surveys that cannot happen until May (bat season). My question are as follows:
-Can we ask for permission to commence work in the ground up to a point?
-Can we start the ground works and drainage at risk?
-They have said it will take 6 weeks for the survey works - do you then have to go back through full planning submission (8weeks)
We currently live in a small two bed house with my daughter and we have a second child due in May so this delay has not only come as a surprised but has caused a lot of upset. I want to try to do everything I can do to minimise the impact of the delay.
Any advice would be much appreciated.
Many thanks
Liam