Hello,
Firstly - I'm sorry about my level of ignorance! I'm a total newbie attempting to build a 40m2 extension to my flat in ICF.
I'm having to use different contractors for the groundworks and the ICF, so I'm trying to get my head around how the two stages meet up...and realising that there are some pretty vast gaps in my knowledge!
The way I currently understand it is that there are three separate concrete pours - filling the foundation trench / concrete slab for the oversite / the ICF walls. Is this correct??
My current plan was to have the trench foundations dug and then filled, then the ICF structure is built and filled, then the interior earth is prepared, insulation laid and slab poured.
Assuming this is right, I'm struggling to see how they fit together when my ICF contractor is solely responsible for building the walls and then filling them; if the DPM has to intersect the ICF, shouldn't the slab be poured once the first row of ICF blocks are down - but doesn't that then mean there's a long delay to finish the ICF while the slab dries?
Is there a much better way of approaching this, one that perhaps avoids having to hire out a concrete pump three times?
Thanks for any help and sorry again if this is a very stupid question!