I have the designs for the timber build with some steelwork which is designed to have the posts down to the concrete foundations which are 750mm below DPC.
My question is should I get these installed prior or post the brick and block work for the foundations up to DPC.
I have a brickie arranged to do up to DPC level but assume I just need to make sure he leaves a gap for where the posts and base plate will be for the steel work but wanted to check before I do something stupid.
I know the ideal might be to do the steel work first but it may take a bit of time to arrange for someone to fit the steels so was hoping to crack on with the brick work first.
Hopefully the attached make sense but it is a left side and rear extension with the thicker black lines on the screenshot photo being the original structure.