SODC delayed the planning decision by requesting a Bat survey that had already been submitted, rather odd. I have had positive support so far and didn't want my programme to slip 🤞
Good to see your finished house and looking forward to getting there this year.
I am just about to sign the contract with Danwood. I had a shock getting a quote from one of their recommended foundation companies. It came in at £66k! I'm hoping to get a much improved cost from a local company even though they have not worked on a Danwood project previously.
My next step is to get the Geotechnical survey as clay and tree roots may mean I have to go for deep pile. Still trying to find a structural engineer and then to appoint the foundation designer. Welcome any advice from others experiences.
Plot purchased 7th Jan, planning decision in 4 days. Plans are finalised and ready to sign build contract. It's going to be a busy year. Look forward to tapping into people's experiences and hopefully get some good advice.