I am new to this forum so apologies if this topic is already covered. I have planning permission to replace my existing 3 bed Dormer Bungalow with a 4 bed detached house with usual materials condition and a drainage condition.
So first attempt materials condition discharged but drainage condition refused. Reason being existing drainage to be investigated and a perc test to be carried out.
we have then carried out perc test which failed due to thick/heavy clay and existing drainage investigated so Foul and Storm goes into combined manhole on my drive.
I attempt 2 we have submitted failed perc test results along with new design showing separate channels for foul and storm before terminating into existing combined drainage (so technically nothing new so using what is already being used for my existing house) This is yet being refused only to be told we should explore other techniques such as green roofs, swales and other above ground detention SuDS etc .
There are separate systems in the road yet all recent conversions (similar to mine, bungalow to house) were allowed to use existing combined systems , it seems mine just bad luck.
My frustration is them keep refusing and not talking or asking for more info, its you pay for a go and then try again..
1. I already have a house so why i can not use use existing system ?
2. Ok if i am not allowed to use existing system and want me to make a new storm connection. Why cant they discharge the condition and i apply for the new connection ?
Really appreciate any advice in advance....