I’ve been searching the forum and the internet to see what the best solid floor build up would be for Ufh, from what I have found, I’m thinking of going with
type 1
sand binding
dpm
150mm pir
dpm
Ufh stapled
100mm fibre reinforced concrete
I’ve suggested this to a couple of companies and they have advised against it and it’s not the correct way it’s done and needs a concrete under the pir and a screed above.
is what I’m suggesting correct or is there a better way? If it is, what spec of concrete would be needed?