Hello Everybody!
We are adding an orangery to the house. After the footings were dug we were told we need piling, I could see that the land had previously been filled in and found all sorts of rubble.
The builder contacted a company who quoted over the phone. No site visit, no soil samples, no structural engineer, no drawings nor calculations.
150mm steel cased piles were driven into the ground about 1800mm apart.
A slurry concrete mix was pumped into the footing and not into the piles. The footing had ground water in it. Initially the piles filled up with concrete, but the last couple of piles filled to the top with water. No tremie was used. Just concrete pumped into the footing expecting the concrete to displace the water a couple of meters down. If poured slowly it may have worked but the footing over the water filled piles was filled to the top very quickly.
I expect that some concrete would have made its way down the piles, but the aggregate probably separated during the long journey through the water and is probably lying on top of the mud that was washed into the bottom of the piles. My bet is that there is water suspended in the middle of the piles.
Does this seem normal, do I have a reason for concern?
I have video of the pouring, where can I go to get an expert opinion?
Should I stop all works?
Desperate for unbiased feedback.
Thanks
C