I have 80m2 of basement floor (5 x rooms + hallway), already laid with ufh pipework. The contractor in the frame for laying a biscuit screeed (sharp sand in an 8:1 mix) 50mm thick, interspesed with battens at 400mm centres is asking for a £9,000 fee, which includes materials & labour for his crew. But here's the thing: the sand (2 x tonne bags) & cement have to be crane lifted over the back wall where there will be 2 or 3 or possibly even 4 mixers on the go (so he says); from there it's a 30 mts walk with wheelbarrow(s), down 3 steps and then a couple more metres to half a dozen more steps and a turn through a conservatory into the property, where the mix is dumped to where 2 x screeders will be doing the tamping and levelling. The contractor's fee works out at £112.50 per. square metre, which seems steep, but I'm not sure whether it is or not, given the logistics of hiring mixers, delivery charges, barrow hire (possibly) moving the mix from the mixing point to where it is needed, etc. Any wise folk out there with an informed opinion on this?