New to this
Members-
Posts
29 -
Joined
-
Last visited
Personal Information
-
Location
Somerset
Recent Profile Visitors
The recent visitors block is disabled and is not being shown to other users.
New to this's Achievements
Member (3/5)
4
Reputation
-
DNO curve ball - Section 37?
New to this replied to New to this's topic in New House & Self Build Design
I believe, from what I discussed with them yesterday, that it's the line itself that determines the situation - and the line to the last pole is a full up 23kVa, the inspector's words were "it's ludricous - that's enough to power about 20 houses, and you only want one". I didn't ask them to consider downgrading the last leg from 23 to 20 or below; my instinct is that would be, as a minimum, a new transformer required, and potentially more complexity / cost / delay? My current workaround is to throw myself on the mercy of my nearest neighbour, ask if I can trench from their pole to the utility verge (I'm sure that's not what they're really called!) and come down the roadside then directly into my plot. It was galling to hear that this legislation is likely to be removed "sometime soon", but not within the timescales of my project - Murphy's Law is how it felt! -
DNO curve ball - Section 37?
New to this replied to New to this's topic in New House & Self Build Design
@ProDave I have tried reading it ... it's not written in plain English! https://www.legislation.gov.uk/ukpga/1989/29/section/37 if you're interested. Google interprets it as: Section 37 of the Electricity Act 1989 requires formal consent from the Secretary of State (or Scottish Ministers) to install or keep installed overhead electric lines above ground. This statutory requirement covers new, amended, or continued operation of lines, primarily those with a voltage exceeding 20 kilovolts (kV). Key aspects of Section 37 include: Purpose: Ensures overhead power line projects are properly reviewed for environmental and local impacts. Application Process: Involves consultation with local planning authorities and statutory bodies (e.g., Natural England, Environment Agency). Exemptions: Consent is generally not required for lines with a voltage of 20kV or less used for supplying a single consumer, or lines on premises already under the control of the operator. Planning Alignment: Often works alongside "deemed planning permission" under Section 90 of the Town and Country Planning Act 1990. Non-compliance: Unauthorized installation or maintenance can lead to legal penalties. It is crucial for network operators to obtain this consent before starting overhead line projects unless specific exemptions apply. My supply line is 23kVa so outside the exemption range. I do feel my DNO (SSEN by the way) have - perhaps - taken the worst possible view and I was not heartened to hear that other DNOs do not all appear to take this interpretation. Apparently though, the DNO will not be budged, their legal team will not allow any other approach. -
DNO curve ball - Section 37?
New to this replied to New to this's topic in New House & Self Build Design
@MPx well done - great result in a tricky situation. My inspector suggested that his DNO were misinterpreting the 1989 legislation and that I shouldn't have this issue at all - who is the DNO for your part of the world, out of interest? Sounds like they have a more pragmatic approach, albeit you've gone around the situation a different way. Mine won't allow me to put a new pole off the last (current) pole. SO frustrating! -
DNO curve ball - Section 37?
New to this replied to New to this's topic in New House & Self Build Design
@NSS not stupid at all - that's exactly what we discussed when the site inspector came today. All depends on the neighbour now to grant permission to use their pole and dig their garden - great shout though -
DNO curve ball - Section 37?
New to this replied to New to this's topic in New House & Self Build Design
Thanks Roger, I will look into that - no harm in researching it -
DNO curve ball - Section 37?
New to this replied to New to this's topic in New House & Self Build Design
@MikeSharp01 when you talk about Planning in this context, what were you thinking please? I'm not getting any sense from the DNO that I need Local Authority involvement (unless Highways end up being involved) - I think it's a case of waiting for the relevant government department to (hopefully) rubber stamp the application. I could, of course be very wrong! For context, I have full planning permission for my development and groundworks start next week. For the last couple of years, the DNO have consistently told me to "wait until I am just weeks away from having the building up, into which the supply will run and smart meter be installed" which is how I'm only finding out now, from the site inspection side of SSEN that there's this issue with the 'last property on the line". -
DNO curve ball - Section 37?
New to this replied to New to this's topic in New House & Self Build Design
Thank you, such a good idea but sadly we're on a low voltage single phase line down a country lane! -
DNO curve ball - Section 37?
New to this replied to New to this's topic in New House & Self Build Design
I love obvious questions - they are the ones I usually overlook!!! No the 'other' direction is hugely expensive due to distance, complex due to actively agricultural fields between us (which increased cost due to depth of excavation 1000mm instead of typically lower amounts. -
DNO curve ball - Section 37?
New to this replied to New to this's topic in New House & Self Build Design
Self sufficiency? Sadly roof shape isn't ideal for that option and we're heavily shaded on the East-South. We had hoped for a modest array on three sides of the hipped roof, but nowhere near what we would need. No mains gas (rural). -
Hi, not sure which forum was the right one so opted for this one. Our new build is in the garden of our existing bungalow, the last property on a low voltage line. Despite over 2 years back and forth with the DNO for quotes for the connection, I've discovered today that they can't do my connection without it going to Parliament (??) to the Secretary of State, under the 1989 Section 37 legislation. The existing bungalow, being the last of the line, and despite having a main electricity line to the pole outside, is not allowed to be followed on by any further build, without said sign off. Which apparently typically takes about a year. I am adding this in as an edit - I don't think it's the Sec of State, reading this from the DNO's own website:- A Section 37 application is a two-part process involving an initial application to the local planning authority followed by an application to the appropriate Ministry:- Scotland - Scottish Government Energy Consent Unit England / Wales - The Department for Business, Energy and Industrial Strategy There are certain circumstances where a supply may be provided to a single customer at less than 33kV without the need to obtain a section 37 Consent. In these situations, it is still necessary to consult with the local planning authority before constructing the line. Where an existing line serving one customer is subsequently required to serve further customers, a retrospective Section 37 Consent will be required. Section 37 consent can also apply in cases where underground cables are being installed from an existing overhead line, where retrospective Section 37 may be required. Where it is necessary to modify an overhead line, Section 37 may be required or in certain circumstances, works may be carried out under the provisions of the requisite Overhead lines (Exemption) Regulations. To say I'm reeling is an understatement. I'm desperate to research whatever I can find now about others who've maybe found themselves in this position, did you manage to deal with it, how, costs etc and what on earth can I be trying next!? Apparently "the quote team should have spotted this" ... but I can see no advantage in my pressing the red button with the DNO, it won't alter the position I'm in now, nor the timescales to overcome it.
-
Excavation levels on clay ground
New to this replied to New to this's topic in General Structural Issues
Our perc test failed for soakaways, so our planning has insisted on all surface water being piped into a drain with a rumble strip and then on out to the ditch. Aren't we fortunate?! -
Excavation levels on clay ground
New to this replied to New to this's topic in General Structural Issues
Thanks @SimonD - I didn't know about the Type 1 vs 3 thing. Is that in the BRegs? My site is quite a decent size and there will be about a third of an acre left after build for water to run off to, if that makes sense, but I've no idea about this stuff and it does concern me I'll run into issues with BC inspections and sign-offs! -
Hoping you experienced folk will guide me; how do I research / know what is the 'correct' ground prep for excavating - in this case specifically site access (needs widening considerably as all construction vehicles need to get from single track lane onto site currently entrance <10m wide) and then the 30+m of sub base that will eventually be finished as our new driveway and also the 2m perimeter around the house for scaffolding, and later for pathways? I haven't chosen a final drive surface yet. Two builders have given figures but I can't compare them as one goes down 300mm while the other 400mm (this is to lay geotextile, then hardcore, then Type 1 compacted, in case that makes any difference). I want to spend the 'most minimum' I can on this without compromising quality; it needs to last once driveway is topped with whatever the final finish is, but I don't want to throw money I don't need at it either. Ground is very high plasticity clay, if that makes any difference.
-
Hoping you experienced folk will guide me; how do I research / know what is the 'correct' ground prep for excavating my access (needs widening - a lot - from single track lane onto site) and putting down the hard standing that will eventually be finished as driveway and also the 2m perimeter around the house for scaffolding, and later for pathways? I haven't chosen a final drive surface yet. Two builders have given figures but I can't compare them as one goes down 300mm while the other 400mm (this is to lay geotextile, then hardcore, then Type 1 compacted, in case that makes any difference). I want to spend the most minimum I can on this; it needs to last once driveway is topped with whatever the final finish is, but I don't want to throw money I don't need at it either. Ground is very high plasticity clay, if that makes any difference.
-
Alterations to detached double garage design
New to this replied to New to this's topic in General Structural Issues
Really appreciate the input @Nickfromwales, @Russdl and @BotusBuild - we are sticking with ONE BIG DOOR 🎉
