I’ve finished reducing the levels of my groundfloor, and ready to lay hardcore, concrete slab and then insulate before laying the UFH pipework.
However i’m unsure how i should be dealing with the door threshold that is a cavity. As my concrete slab level is higher than the internal leaf. The required level for slab is top of wood in photo.
How should i go about avoiding the cavity from being filled with concrete? And getting dpm fitted correctly.