Hi All,
This is my 1st post so hopefully I'm not sounding too stupid!
We have obtained a Party Wall Agreement between ourselves and the owner next door. We have done the 14 day notice when received the document and before we started any work. The builders have removed the old wall and chimneys, however they are now looking to re-build the wall with the adjoining neighbour. As they will need access to their side, and this is the part I am getting confused, do we need to serve 14 days notice again? There's nothing in our agreement on this and it's what I've come across on a few websites. Also we have a difficult neighbour and our agreement is with the landlord, so we were going to notify the landlord to communicate with the neighbour when we intend to do the work and need access their property so to tell their tenant.
Just wanted to ask if anyone has had a similar situation and if we do need to do the 14 day notice again?
Thanks in advance,
M