Hi there,
I've a 125m2 extension being erected next year with a pretty basic floor slab planned.
Floor covering
65mm Screed
UFH Pipwork
150mm PIR insulation
100mm c35 concrete with mesh
Whilst looking at the overall prices of each piece of work there's a couple of questions that have come up
would it beneficial to change the floor structure to incorporate circa 250mm of eps insulation under the concrete slab, instead of the 150mm pir a