From the blog "Rose Lane re-build"
Initial post date 21 Jan 2016
Our planning application took just over 3 months, however there was a lot of work done before this. As I said previously over an extended period the plans bounced back and forth between the Architectural Technologist (AT) and myself, with the occasional face to face when I was up at the existing house.
The initial submission consisted of the topographic survey and photographs I posted last time, a OS map (very out of date, but required), Application form and