Has anyone come up against the new Part R implemented 26th Dec 22?
Our independent BC have said they need us to provide a connectivity plan for our new build but I've got lots of issues around this as no-one seems able to explain it to me in a way that makes sense
Firstly when I read the Openreach website it specifically says if planning permission was granted before 26th dec it doesn't apply - BC are saying that's not right & that the BC application would need to have been