Hi,

 

Looking for some advice here as works have gotten under way on my modest kitchen extension on my home in SW London (Merton). My builder and I realised my architect has not correctly added the 600mm dog leg return (highlighted in diagram) that is on the rear of the house. This means the flank wall will be 5.1m instead of the 4.7 -4.9m (varies on different elevations) on the approved drawings (attached). The Shared boundary wall will be 4.5m and this is what the planning officer mentions in her report. So I suppose my question is that as long as we build 4.5m on the shared boundary which happens to be the side of the house that protrudes further then does it matter about the depth of the flank wall?

 

My builder and architect both seem to think it will be fine but looking for second opinions as they wont be the ones left holding the baby if some one comes knocking.  Many thanks in advance.

 

 

DR1.jpg

DR2.jpg

Floor Plan.jpg

Edited by MrMonkey
addtions

Share this post


Link to post
Share on other sites

This only came to light yesterday afternoon so have not had correct drawings made up yet. This is one of the original drawings that shows the dog leg albeit at 400mm instead of 600mm but is the 1st floor elevation.

 

 

Fp2.jpg

Edited by MrMonkey

Share this post


Link to post
Share on other sites

I agree with your builder and architect that it will probably be ok. The only thing that might cause a problem would be your neighbour on the "flank wall" If they notice this change they might kick up a fuss.

 

Personally I would not let it stop works, but I would tell the architect he must indemnity you against any enforcement action because of his error and cover the costs of correcting the drawing and of making a "non material amendment" planning application. There is no chance it will be refused.

 

You could get away without the extra planning application, but when you come to sell an eagle eyed buyer might spot it. Far better to get it sorted out properly now.

Share this post


Link to post
Share on other sites

Thanks for the response, I have actually reached out top the planning officer directly to confirm then I can re-submit based on her response.

Share this post


Link to post
Share on other sites

If you've highlighted it to the planning officer they will advise that you need to go back through the planning process - it will also mean you have no option at indemnity policies etc if you sell the house

Share this post


Link to post
Share on other sites

You really needed to get your architect on side and doing the drawings before you let the cat out the bag

Share this post


Link to post
Share on other sites

Create an account or sign in to comment

You need to be a member in order to leave a comment

Create an account

Sign up for a new account in our community. It's easy!

Register a new account

Sign in

Already have an account? Sign in here.

Sign In Now