Jump to content

Concrete Sub-floor prep for ufh


JFDIY

Recommended Posts

My Sub-floor slab was put down in less than ideal circumstances, it froze overnight on the days after and I covered it in sheets and bales of straw to protect it. The timber frame guys needed to work from it only a few days after and where timbers allowed water to run off/drip the surface layer has suffered with areas where the surface is loose and when cleaned away leave a 3-5mm lower surface which is rough

 

Anyway two years on I'm getting ready to move on with insulating with PIR ready for underfloor heating pipework, screeed etc.

 

My concern is that the sheets of insulation will be over the rough areas and not have full support, what do people recommend, should it be made good in some way, if so what with?

 

IMG_20200211_153857827.thumb.jpg.c228015e7316eeafe2cc72827540dfc8.jpg

 

IMG_20200211_153925258.thumb.jpg.7b47d76901538e2c10c9f84ad05a014f.jpg

 

Link to comment
Share on other sites

It really won’t matter if the floor is uneven Especially if the sub floor is just a bit rough once the membrane and insulation is down 

The weight of the screed will help even things up and leave a flat surface 

Link to comment
Share on other sites

7 hours ago, BMcN said:

Mix up some sand and cement at 8:1 and a splash of water so it clumps together and roughly level.

 

7 hours ago, epsilonGreedy said:

Thin flow screeds present a bigger problem because there is less weight pushing down on the insulation sheet.

Definitely 

Great for tiling on but you need the floor to be pretty even for flow screed 

With a typical semi dry screed on a floor of 150 m2 You will have 20 tons of screed flattening your insulation 

  • Like 1
Link to comment
Share on other sites

20 hours ago, BMcN said:

Mix up some sand and cement at 8:1 and a splash of water so it clumps together and roughly level.

 

Sounds ideal, I was thinking of almost a neat cement mix, or at least a strong mix. I think the skin of 'fat' on the cement is what has been affected by being constantly disturbed by dripping water. The slab is 5" thick and otherwise sound, just needs a bit of levelling where the surface is flaky.

 

Would you wet the area to promote adhesion, or use any special primer?

Link to comment
Share on other sites

That will be a layer or laitance, caused by excess water or over floating normally.  

 

No I wouldnt bother, as long as its roughly flat so the boards done rock around.   On my sub floor it was quite uneven so before laying the insulation I put down between 5-40mm of a sand cement screed so I had the correct depth on top for my flowing screed.  Far cheaper than maybe for 2 or 3 extra cubic meters of screed.

  • Like 1
Link to comment
Share on other sites

I think you're right, It's very chalky and if you get under an edge it flakes off quite easily. The concrete underneath is quite a bit harder, but also rough. 

 

Not sure if I should try and chip it all off the surface (75m sq) or just try and make fairly flat. There's going to be 130mm or 150mm insulation and 50mm of flow screed with ufh.

 

Tiles on top and I don't want it to crack.

Link to comment
Share on other sites

I did mine a couple of months ago.

 

We laid the 120mm PIR on the sub base, in some areas it rocked a little, so we adjusted the boards so that the board joints were on the high points so it didn't rock - the boards are never 100% flat.

 

A couple of boards moved up / down a few mm when walked on - when asked the floor screeder laughed and said that is fine, in fact its one of the best floors I have seen, I get floors that are like seesaws and the screed holds the boards flat.

 

We had Cemfloor screed - we fitted expansion strips where recommended - we have a couple of hairline cracks in the screed exactly where the floor screeder said it would crack due to the size and shape - he said that hairline cracks are nothing to worry about and that if I was concerned, then just use an epoxy crack filling kit.

 

I see that you are in the Midlands - PM me if you want the details of our screeder and the UFH fitter - I would recommend them both.

Edited by wozza
  • Thanks 1
Link to comment
Share on other sites

  • 1 month later...

I have a similar problem with my concrete slab in that it is very rough. I have raised ridges as well as some depressions and I am concerned they are too big to just leave - there will be a large amount of rocking and some areas where the insulation is not properly supported. I was wondering the most suitable (and cost effective) way to level the worst of this before I lay the sheets of PIR. It's actually worse than the photos make out. Would a sand and cement slurry work? Or a thin sand blinding? Or would i need a proper levelling compound? Obviously it's only to get it somewhere close to level before I lay the insulation. There will be a 50mm liquid screed being laid on top.

 

IMG_2985.jpg

 

IMG_2986.jpg

Edited by DaveH
Link to comment
Share on other sites

2 hours ago, DaveH said:

I have a similar problem with my concrete slab in that it is very rough. I have raised ridges as well as some depressions and I am concerned they are too big to just leave - there will be a large amount of rocking and some areas where the insulation is not properly supported. I was wondering the most suitable (and cost effective) way to level the worst of this before I lay the sheets of PIR. It's actually worse than the photos make out. Would a sand and cement slurry work? Or a thin sand blinding? Or would i need a proper levelling compound? Obviously it's only to get it somewhere close to level before I lay the insulation. There will be a 50mm liquid screed being laid on top.

 

 

 

 

 

12mm EPS layer first and reduce the PIR slightly as the EPS will crush down

Link to comment
Share on other sites

Create an account or sign in to comment

You need to be a member in order to leave a comment

Create an account

Sign up for a new account in our community. It's easy!

Register a new account

Sign in

Already have an account? Sign in here.

Sign In Now
×
×
  • Create New...