Would like some opinions on this please.

 

Once our house was built we parted ways with our builder as he didn't turn up as scheduled (and wouldn't tell us when he would turn up) to complete the landscaping, paving and driveway. We found a new builder who included quantities in his quote. Now that the work has been completed he is saying that he had to use a depth of 250mm hardcore instead of 150mm underneath the paving (paving is around the perimeter of the house at door level), which is an additional cost of £750.

 

Also an additional £750 for a surface/channel drain on the tarmac drive as it's 30% longer than he thought it would need to be.

 

Should I pay this extra when he was able to see the ground conditions, level of completed house etc, between him quoting to do the work and him starting the work, nothing changed on the site.

 

 

Edited by ultramods
Link to comment
Share on other sites

That would really get my back up. If there was such a huge "extra", they should agree it with you not do it and then tell you at the end. Me personally, I would never rip off a trade, but I wouldn't be paying that. He gave you a price and should stick to it!

  • Thanks 1
Link to comment
Share on other sites

Quote or Estimate ..?? 
 

250mm up from 150mm isn’t that much - it’s about 7sqm/tonne of MoT1, which at £35 a bag would be that he laid an additional 75 or square metres (inc labour) then it is probably about right otherwise it seems steep. 

Link to comment
Share on other sites

1 minute ago, Mr Punter said:

The costs to distribute the hardcore should be similar as he already had the machine and driver, so it is extra material.  Do you know the square area?  Ask him for invoices for the hardcore.

 

Yes' it's just an extra material cost for the hardcore, yes I have the area. But if I ask for invoices and they needed more materials, do I then need to pay.

 

What irritates me is that he could have quoted lower and then added the "extras" when he knew that the extra quantities would be needed all along.

 

However I suspect for the drain it's time and materials.

Link to comment
Share on other sites

3 minutes ago, PeterW said:

Quote or Estimate ..?? 
 

250mm up from 150mm isn’t that much - it’s about 7sqm/tonne of MoT1, which at £35 a bag would be that he laid an additional 75 or square metres (inc labour) then it is probably about right otherwise it seems steep. 

Quote.

 

It's 103 m2 of paving

Link to comment
Share on other sites

When I gave a quote for work I always said if any additional materials or work was required a price would be agreed before work progressed, yes it’s only 9% but it’s still £1500 ? I would be miffed.

Link to comment
Share on other sites

You are more annoyed about the lack of communication than the price I feel.

 

Bad or non-existant communication is par for the course in this sector. How about this......

Pay what you agreed straight away. Pay the rest in stages ... it's easy to find a rationale for the delayed payment.

He might think twice about not telling a customer next time.

 

Yeah, right ....

Link to comment
Share on other sites

Tricky one.....when I used to quote For work on a regular basis it was for the full job, everything was itemised and it was very clear what was included. If I got it wrong then I would have to just suck it up and cover the extra costs. However if there was an anomaly on the job that could not be seen During the survey  (I was building a road once and there was a hidden cave bellow the road...) then after a meeting that extra work would be carried out at the agreed (at the start of the contract) day / hourly rate and any additional materials would also be covered by the client. Once your quote was in and it had been accepted there was no going back and revising it...... this was all government contracts so slightly different.

Link to comment
Share on other sites

Not incredibly helpful I know but I found our groundworker the absolute worst for prices going off piste during the job and unexpected costs being added on without any real discussion. We did pay them but were very careful to manage things differently after that as we had more work for them to do. Not much help if it's at the end of your job but TBH I would probably just pay and write it off as a poor experience. If you're happy with the work other than that, and you've actually managed to get someone in to do it then there are some positives. A bad job would be much harder to swallow than a good job that cost a bit more in my opinion. 

Link to comment
Share on other sites

I'd be pi$$ed off too, but you need to decide if it's worth falling out over.  If you're happy with the job, I think I'd pay up promptly for the agreed bit and smile and ask nicely if you can come to some agreement about the extra as it wasn't in the budget.  Anything you can claw back is a bonus, and as @newhome said, at least he hasn't cut corners and done a poor job...

Edited by Roundtuit
Link to comment
Share on other sites

1 hour ago, joe90 said:

Whenever I got someone to quote I made sure I was in tatty working clothes and mentioned my budget was very tight, this usually made sure they didn’t rip me off and talked if extra was foreseen ?

While standing outside your 2.5 million dollar property.........  only kidding, good strategy if it’s in context. 

  • Haha 1
Link to comment
Share on other sites

1 hour ago, joe90 said:

Whenever I got someone to quote I made sure I was in tatty working clothes and mentioned my budget was very tight, this usually made sure they didn’t rip me off and talked if extra was foreseen ?

 

I use a similar strategy, I'm pretty good at scruffy anyway but I make sure I take my wife's 5 year old permanently filthy car when meeting someone for a quote. 

  • Like 1
Link to comment
Share on other sites

1 hour ago, Ed Davies said:

Had scrappies knocking on the door the other day to ask if I wanted to get rid of my van. Is that about right?

Yup.... they leave there business cards on my landrover window all the time........ 

  • Like 1
Link to comment
Share on other sites

Create an account or sign in to comment

You need to be a member in order to leave a comment

Create an account

Sign up for a new account in our community. It's easy!

Register a new account

Sign in

Already have an account? Sign in here.

Sign In Now
×
×
  • Create New...