Jump to content

Annker

Members
  • Posts

    76
  • Joined

  • Last visited

  • Days Won

    1

Annker last won the day on April 19

Annker had the most liked content!

Recent Profile Visitors

777 profile views

Annker's Achievements

Member

Member (3/5)

18

Reputation

  1. Thanks for the prompt. Actually I do recall now that indeed they work plainly awful.
  2. I've to make the same kitchen design layout choices myself in a few months time. The recirculating hob/MVHR combo is a tidy solution but I have a vague recollection of hearing that it (recirculating extraction) isn't that effective, so for me dedicated hob extraction to the outside is my default as I know that works.
  3. The issue with having the hob in the island is it makes extraction a more of a problem.. You will either have hood extraction hanging from the ceiling potential ruining slight lines or an expensive downdraft extraction which will require the ducting to be buried under the floor. Secondly the route the extraction ducting will take will be longer and more torturous vs having the hob on an external wall.
  4. I have considered a parge coat. Given I've ~130 sqm of walling to cover, it would be a significant addition cost so I am debating if it is required Firstly, the internal face of the walls are plumb floor to ceiling but there are discrepancies in flatness. So a parge coat would fill out those discrepancies and hollows that otherwise may exist and I imagine could provide space for moisture to gather. Secondly, as you say a parge coat would fill any brickwork joints, and there are a few joints that aren't fully filled. However is the parge coat required to provide an airtight barrier? Going down the vapour closed route the PIR layers, and their perimeter, will need to be meticulously sealed, that is critical for the system to work. I need to ensure that provides an airtight layer. I wonder if I can consider a parge coat would optional second line of airtightness defence that I dont need to spend money on, or perhaps I should consider it as a critical component.
  5. The existing internal wall lining on the externals wall is lath & plaster, all of that will be removed so the proposed IWI will be on to barefaced brick.
  6. @Mike Yes I agree that a vapour open system put together with natural fibres fairs better should significant amounts of moisture penetrate the external brickwork. My hope is that that favourable site conditions (well sheltered semi-d, lime pointed brickwork, floor levels ~300mm to 900mm above external GL) and a conscientious install of the VB should eliminate or at least minimise moisture levels within the wall being raised to a level that will cause issues. I have read elsewhere alright that Ubakus is not that comprehensive. I played around with the outside temp & humidity values to somewhat compensate for that. It was interesting to see that with the outside temp set to -10 degrees the model with 60mm PIR remined condensate free. However condensation was indicated in the model with 60mm wood fibre (screen grab below) Not sure if that observation has any validity/relevance.
  7. @FrankHouse Understand this is an old post but if you get the @ notification I would love to know if you went ahead with the IWI as outlined in your post and if so how it has performed?
  8. Thanks for the response @Iceverge I am fortunate with regard workmanship/QC as I am a carpenter by trade (consider myself to have an eye for detail) and I will be doing the work with my own team. And I also have an appreciation for the level of attention that correct installation of an airtightness membrane requires. As my original post I have endlessly read every facebook group posts, forums, etc in researching IWI options. PIR got eliminated for consideration early on, almost entirely due to the absolute contempt the heritage/lime community have for it. Obviously they have a bias but it can be hard to ignore. That led me down the path of vapour open/breathable system, however not being a die hard conversationalist I still wanted to integrate the buildability of modern solutions into the mix. I also follow a house renovation channel on youtube which recently uploaded a video of a hybrid system called SWIP, and that in short is how I ended up with the bastard solution above with a foot in each camp if that makes sense. There is so much conflicting opinion regarding IWI that I'm ready to pull my hair out with analysis paralysis! . I personally have not had, or seen a PIR IWI cause damp/mould, and it is a system I would prefer. I feel there is too much broad strokes when discussion the various systems. The only differences debated are of the systems themselves; relevance of where (location, orientation, aspect) and how (workmanship) is ignored. So I must say its a relief to hear some experienced hands form this forum give a vote for PIR! I have modelled the PIR solution on Ubakus, and to me it looks ok. Humidity doesn't approach saturation point which I imagine is the most important thing.
  9. Typically needles penetrate the building in the room above the room where the steel is being installed. Yes they are disruptive and result in more remedial works but they are a significantly more robust and safer method of providing temporary support vs strongboys particularly in wide openings such as yours. No doubt strongboys and back propping joisting is used also by some, ultimately it's your call.
  10. Yes you certainly will need temporary support of the external leaf. That is a significant opening and if I understand correctly has two storey of brickwork above it. Similarly I'd question supporting the inner leaf by solely propping the existing joisting. Sounds to me like a job for needles penetrating both leafs.
  11. Thanks for the response. I know you have posted a lot on the subject and believe me I have read reams of material on the subject and still can't confirm my spec! Agreed that hygroscopy may be an issue with gypsum and my initial thought was that gypsum could not be used in vapour open system but as my original post it is a recommended detail from Back to Earth. Surely given where the PB and skim layers are located in the build up condensation should not be an issue. Modelling shows the Dewpoint within the insulation albeit it is towards the warmside; perhaps you saying the concern is if the Intello membrane allows vapour to travel outsode to inside should relative conditions drive it so?
  12. Dear all, I am looking for some design critique on a IWI design which I am planning to install in my Victorian semi-d renovation project. The existing walls are 9" solid brick with original lime mortar jointing and the house is sited in a relatively sheltered urban location in Kent. Following weeks of reading the wide array of opinions regarding installation of IWI to a solid walled house I have arrived at the buildup below with two different insulation options: Internal to external Breathable paint finish Gypsum skimcoat Gypsum Wallboard 12.5mm Service cavity 38mm x 50mm battens @ 400mm c/c Intello plus VCL 60mm Breathable Insulation layer OR 60mm PIR foil backed Insulation/VB layer 225 solid brick wall *Existing The design follows the "warm batten" arrangement. Preference is for a vapour open design and use breathable insulation, however I am unsure what specific type product could be used in that instance. I imagine the insulation would need to somewhat resist compression from the battens so perhaps batt type format. HAs anyone used a glass or mineral wool slab in a similar situation? Wood fibre is a candidate but it is pricey. I believe a vapour closed design has more risk in terms of trapping moisture within the buildup, however PIR insulation with its relatively high compressive strength lends its well to the warm batten design so this option is easier to spec material wise. After much reading I am satisfied that a gypsum plasterboard and finishing coat can provide a satisfactory degree of vapour permeability, hence their inclusion. Some will disagree (some who worship at the Lime Alter will be horrified) however there are studies that suggest that gypsum is more "breathable" than lime. I actually spoke to a tech/sales member of staff of a well known eco & natural BM and he (of his own accord) said he regards gypsum as entirely suitable in some IWI system build up, in fact they have it specified in some of their IWI solution on their website.
  13. Exactly this. Sure the entire world is sitting on liquid molten material and its going nowhere (save a few earthquakes!)
  14. 10mm gap along both plywood to plywood junctions and the perimeter of the room. Plywood doesn't expand along the length or width of the sheet to any degree that requires consideration in this scenario. I used Hardwood faced ply as opposed to softwood faced shuttering ply. In the absence of the floor having any direct fixing to the underlying substrate, it is prudent to lay up the subfloor with materials that remain general flat rather than warp if you look at it sideways like shuttering ply The floors I was installing were generally all hardwood T&G flooring, secret nailed and occasionally may have some inlay work. And for that particular installation I would rate plywood above OSB. I feel plywood has a more robust surface for installation; nailing, marking out on etc.
  15. I've installed hardwood timber floors in many houses using the floating floor method and it performs exceptionally well. I actually revisited a house over christmas where this was done in 2006 and the home owners reported the floors are as stable as the day the were installed, I believe 17/18 years is a sufficient test duration! I believe the buildup was: 18mm oak T&G boards 12mm hardwood ply (laid half bond at a 45 degree and screwed to the ply layer below) 12mm hardwood ply (laid half bond and loose over the PIR) 120 PIR Sheet DPM Concrete subfloor
×
×
  • Create New...