Jump to content

Leaderboard

Popular Content

Showing content with the highest reputation on 11/07/17 in all areas

  1. First fix started and i will say its going well. My SunAmps arrived today. Need day off to rest, they weigh a tonne. well 170kg actually Shown with tops off
    1 point
  2. Woohoo! Consent to Discharge approved!
    1 point
  3. Scaffold down at long last. still need to have the oak porch and oak balcony fitted
    1 point
  4. The only thing I'd add to that would be ditch the S plan and feed the TS direct from the boiler. Feed the Ufh from the TS, it's a far better solution than running off the boiler imho, and go for a boiler which can match your max dhw flow ( kW that the dhw coil can provide ( 28mm coil and TMV is circa 46kw )). It'll not need to idle then as it won't be serving Ufh on demand, instead it'll be pulsing higher grade heat into the TS thus optimising the temp range and condensing efficiency will be maximised.
    1 point
  5. That might make sense if you look at fuel costs only, but if you factor in the additional running and captial cost of having BOTH technologies does it still stack up. Very simplified example. 100% gas: boiler cost £600, installation £1,000 annual fuel cost £600 annual service £50 20 year total £14,600 100% ASHP: pump £2,000, installation £2,000 (includes hard-standing and piping for external unit) annual fuel cost £550 annual service £50 20 year total £16,000 Both gas and ASHP: capital cost £5,600 annual fuel cost £575 annual service £100 20 year total £19,100 Above is very simplified and does not factor in inflation, nor the extra running costs or extra capital costs in integrating the gas and ASHP (e.g. larger TS, more controls, more pumps). Costs I use are for illustrative purposes, you need to plug your own scenario in. I would suggest you go with gas only, put in a largish TS (e.g. 500l based on your concurrent bath / showers scenario), put in a gas boiler based on DHW recovery times you are willing to put up with (12kWh boiler to 500l TS is approx 2hrs recovery from cold), and use a standard S-plan configuration to run UFH direct from the boiler (no separate buffer). In 20 years time, if gas becomes prohibitively expensive, then revisit the solution based on latest technology. (In reality, our electricity base is derived by burinng gas so increase in gas price also impact electricity price).
    1 point
  6. Well my stairs arrived from Staribox today. Managed to get the top flight in. Unfortunately there is a problem with the two newel posts that join the top and bottom flight. They don't fit and they have finished the top detail incorrectly. I have emailed stairbox with pictures. Unfortunately, until that is resolved I can't fit the lower flight (which in itself looks correct)
    0 points
×
×
  • Create New...