Jump to content
  • entries
    9
  • comments
    51
  • views
    4754

A tale of 3 Lockdowns


BotusBuild

1670 views

I left the site in November 2019 with the two trees felled, and we had decided that the design and approved planning application were not quote to our liking, so we took the decision to put in a variation of condition which went in for consideration in December 2019?

Little did we know what this would mean to progress; as we are building very much at the DIY end of the self build spectrum, and not living close to site, by the time we had the go-ahead we were in Lockdown 1.0 and unable to get to site until July 2020.

But before that, I'd already started the applications to install water and electricity, so in the first few months of 2020, I had lined up the water installation and had most of the things in place for the electricity connection. The water was due to go in at the end of March, and as you can expect, this was postponed. However, by keeping in touch with my local ground worker, the two neighbours and hte water and electricity folks, we were able to get things lined up to get both connected in the same week in July. Also, our local ground worker convinced us to push an access straight from the lane down to where we were building - I recommend listening to the experienced ?

20200722_202918.thumb.jpg.a4af6a02bc9b2bada0fd3fa29d044b9b.jpg

 

As well as getting things in place for our return to site, we took the opportunity to source a caravan that we could put onsite in order to make it easier to be able to travel straight to site and not have to rely on being able to use the local TravelLodge - little did we know how useful that was going to be.

 

20200722_202859.thumb.jpg.161cde847b9472a610c5ee24157ebe36.jpg

 

So, in June and early July a couple of short preparatory trips

  • moving the caravan to site and setting up,
  • connecting the water standing pipe,
  • installing meter boxes,

then in July - October, we made several trips to

  • clear and burn vegetation,
  • feed and water the water and electricity teams,
  • have meals with our "to be" neighbours,
  • take delivery of a septic tank
  • dig a lot of holes
  • lay drainage pipes
  • fit a septic tank
  • fill holes with stone
  • fill holes with spoil

and finally start digging a very large foundation hole for the insulated raft foundation

 

20200905_131317.thumb.jpg.bc5187eeb43d3f232fc85d0d1d6c37b6.jpg20201013_151435.thumb.jpg.69a442aac6bb879de9ccb7465a766bf6.jpg20201016_160723.thumb.jpg.9421602f8496d16911257372fa44e276.jpg

 

And then we hit Lockdown 2.0 - another month of enforced "stay away from site", then in early December, I returned for two short visits to finish off concreting in the drainage pipes that will end up feeding through the insulated raft.

 

20201128_150342.thumb.jpg.3a43b315b2dac51de110b9aa00184f63.jpg20201128_150409.thumb.jpg.6cf140d78f87f8ee22cafa12f51e0803.jpg20201128_162525.thumb.jpg.ec42d42ca1592af219c8696086dc396b.jpg20201205_102733.thumb.jpg.70bf37f807e62027dff99f2731f0c617.jpg

 

And so we find ourselves in Lockdown 3.0 during which

  • we are sorting out re-mortgaging to a lower fixed interest rate, which we always knew we would do, but we had hoped to be a lot further along ? 
  • choosing insulated raft supplier
  • determining steel re-inforcement requirements
  • and, due to delays, considering moving slightly along the self build spectrum towards more use of subcontractors ?

 

And so as I write this with the Calcutta Cup on in the background wondering how long it will be before the travel restrictions are lifted, but planning for a late March trip West.

 

 

 

  • Like 3

6 Comments


Recommended Comments

All progress is some progress! We are in a very similar situation with living in the south east and building in East Cornwall - we haven't been there since October when we had the topsoil scraped off (one of the planning conditions as the area has raised levels of arsenic in the ground). We can't wait for lockdown to lift so that we can get down and start some work.

  • Thanks 1
Link to comment

Yup, looking good, and any progress is good at this time, thankfully things look less bleak for the future so onwards and upwards ?.

  • Like 1
  • Thanks 1
Link to comment
22 hours ago, Ferdinand said:

The double socket in the meter box is a very good idea.

I thought - the more the merrier ?

 

The plan is that the contents of the right hand meter box will end up in the garage

Link to comment
18 hours ago, Omnibuswoman said:

We can't wait for lockdown to lift so that we can get down and start some work.

The restrictions have made me think about more use of contractors if the delays get too much. We will be keeping this is review as time progresses - and the end of the fixed rate on the mortgage approaches ? 

  • Like 1
Link to comment

Create an account or sign in to comment

You need to be a member in order to leave a comment

Create an account

Sign up for a new account in our community. It's easy!

Register a new account

Sign in

Already have an account? Sign in here.

Sign In Now
×
×
  • Create New...