Jump to content

Foundation 3 - Blockwork


Thedreamer

2353 views

Last week we poured our concrete strip foundation and we have now moved onto the block work. Monday was a day of stacking the first blocks, taking measurements and setting up lines. By the end of Monday we were all ready to start with the first course in the morning. 

 

P1140741.thumb.JPG.464f8fa9b6ba8cee15521a291567b6d6.JPG

 

 

By the end of the Wednesday we were at:

 

P1140745.thumb.JPG.597b6f1a1bde1a0b291890ff2bcdaad2.JPG

 

 

By the end of the Thursday, a lot more blocks were delivered and we were at:

 

P1140771.thumb.JPG.b6835b440617e58517d62ccf7c6cc4c0.JPG

 

The good weather continues into the second week and so does the progress on the blockwork.

 

DSC00407.thumb.JPG.e02ced4111c1f13b9e6f25b176028362.JPG

 

DSC00411.thumb.JPG.db47750fab003f6dc4818da08d81e9d9.JPG
 

A little job during the weekend, trenches now dug and ready for the plumber to put in waste drainage pipes 

 

P1140799.thumb.JPG.5dde33533388b9866dba4af0df99512e.JPG

5 Comments


Recommended Comments

3 minutes ago, Tennentslager said:

FFS get a move on...?

 

The weather has been good this week in Skye, hopefully it will continue. 

 

Our Brickie is doing a great job, he is here at 8.30 and works till 7.

 

I did one day in stacking blocks and busted my back, I don't how these guys do it. 

 

Link to comment
2 minutes ago, PeterW said:

Bet you they have a working bathroom by August at this rate .... unlike some ..! 9_9

 

As long as the house is wind and water tight by around the Autumn, I'll be happy with that. :)

 

The joiner wants to start cutting the kit on site early in May.

 

 

 

 

 

Link to comment

Create an account or sign in to comment

You need to be a member in order to leave a comment

Create an account

Sign up for a new account in our community. It's easy!

Register a new account

Sign in

Already have an account? Sign in here.

Sign In Now
×
×
  • Create New...